40m work plan (edited Jun 2017)

Planning

This google document collects some project ideas for the short/medium/long term.

Some ongoing projects (in rough order of priority), updated on Jun 5 2017:

Long term future

Mid term future

Near term targets

Paper worth topics


Old materials. To be merged to the above info

This should be kept up-to-date. This is an overview of our near-term goals. We can link to other TODO lists from here.

PRMI commissioning

DRMI

This and FPMI are the next primary tasks. We will need to vent to flip SR2 first, although we need better calculation of the PRC/SRC coupled-cavity affect on the SRC mode.

End table upgrade

This is needed before we move on the FPMI commissioning.

FPMI

We obviously need both end tables fully functional before we get to this.

PRFPMI

DRFPMI

Next vent

Will need to vent soon to flip SR2.

Longer term: