Size: 1989
Comment:
|
Size: 3145
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 3: | Line 3: |
| == Major Mission == | == Major Missions == |
| Line 5: | Line 5: |
| . Binary Outputs . RFM . Simulated plant for Green locking |
. {*} Make the Binary Outputs work on C1SUS and damp the vertex suspensions . {*} Make the Reflective Memory Network work . {*} Simulated plant for Green locking |
| Line 17: | Line 17: |
| . attachment:orange.png Binary Output working (Alex/Joe) 1-2 days | . ''' Binary Output working on c1sus (Alex/Joe) 1-2 days ''' . attachment:orange.png test all the BO channels and their assignments . attachment:red.png Switching over cabling from the current XY220's to the new system |
| Line 19: | Line 21: |
| . attachment:orange.png Complete suspension damping keeping in mind Version B coils. (1-2 days?) . attachment:orange.png Get RFM working! (We have new parts and need new IPC parser) (3-4 days) |
. ''' Complete suspension damping keeping in mind Version B coils. (1-2 days?) ''' . attachment:green.png damping all the vertex suspensions with the new CDS . attachment:red.png check if the binary outputs are working |
| Line 23: | Line 25: |
| . attachment:red.png Get both end stations working. Check we have correct number of cables (againi tomorrow). | . ''' Get RFM working! (We have new parts and need new IPC parser) (3-4 days) ''' . attachment:green.png string the RFM optical fiber connecting C1SUS and C1ISCEX . attachment:orange.png install PCI-5565 driver on c1sus . attachment:red.png install PCI-5565 driver on c1iscex . attachment:red.png test the RFM card by running the diagnostic script on the individually . attachment:red.png test the RFM with the epics |
| Line 25: | Line 32: |
| . attachment:red.png Get IOO working. (Get thing computer into 1X1 or 1X2 rack, get IO chassis into 1X1 or 1X2 working. (5 days) | |
| Line 27: | Line 33: |
| . attachment:red.png Simulated Green Locking. | . ''' Get both end stations working ''' . attachment:red.png Check we have correct number of cables (againi tomorrow). . attachment:red.png Check if both end stations are correctly running . ''' Get IOO front end machine working ''' . attachment:red.png Get thing computer into 1X1 or 1X2 rack . attachment:red.png get IO chassis into 1X1 or 1X2 working. (5 days) |
| Line 29: | Line 41: |
| . attachment:red.png Either Green locking or simulated plant LSC (or in parallel). | . ''' Simulated Green Locking ''' . attachment:red.png conceptual design . attachment:red.png make realtime simlink model . attachment:red.png compile and install the model |
| Line 31: | Line 46: |
| . attachment:red.png Fix non-working IO chassis (today). Check on fiber with Rolf for LSC. | . ''' LSC simulated plant ''' . attachment:green.png conceptual design . attachment:green.png make realtime simlink model . attachment:orange.png compile and install the model . ''' Fix non-working IO chassis ''' . attachment:red.png Check on fiber with Rolf for LSC . attachment:red.png time |
September CDS plan
Major Missions
Make the Binary Outputs work on C1SUS and damp the vertex suspensions
Make the Reflective Memory Network work
Simulated plant for Green locking
PLANS
TO DO LIST
attachment:green.png complete
attachment:orange.png intermediate state
attachment:red.png incomplete
attachment:black.png gave up
Binary Output working on c1sus (Alex/Joe) 1-2 days
- attachment:orange.png test all the BO channels and their assignments
- attachment:red.png Switching over cabling from the current XY220's to the new system
Complete suspension damping keeping in mind Version B coils. (1-2 days?)
- attachment:green.png damping all the vertex suspensions with the new CDS
- attachment:red.png check if the binary outputs are working
Get RFM working! (We have new parts and need new IPC parser) (3-4 days)
- attachment:green.png string the RFM optical fiber connecting C1SUS and C1ISCEX
- attachment:orange.png install PCI-5565 driver on c1sus
- attachment:red.png install PCI-5565 driver on c1iscex
- attachment:red.png test the RFM card by running the diagnostic script on the individually
- attachment:red.png test the RFM with the epics
Get both end stations working
- attachment:red.png Check we have correct number of cables (againi tomorrow).
- attachment:red.png Check if both end stations are correctly running
Get IOO front end machine working
- attachment:red.png Get thing computer into 1X1 or 1X2 rack
- attachment:red.png get IO chassis into 1X1 or 1X2 working. (5 days)
Simulated Green Locking
- attachment:red.png conceptual design
- attachment:red.png make realtime simlink model
- attachment:red.png compile and install the model
LSC simulated plant
- attachment:green.png conceptual design
- attachment:green.png make realtime simlink model
- attachment:orange.png compile and install the model
Fix non-working IO chassis
- attachment:red.png Check on fiber with Rolf for LSC
- attachment:red.png time
- attachment:red.png Simulated Green Locking.
- attachment:red.png Either Green locking or simulated plant LSC (or in parallel).
- attachment:red.png Gentoo patch (not high priority - unless they stop making backwards compatibility - do it when we have time).
TIME LINE SCHEDULE
- Put time line schedule here.
DETAILED CONSIDERATIONs
Cable Requirements
- Do we have sufficient number of the cables ?
- Let's doublecheck it.
Notes about Binary Outputs
- How to make a bitwise
- relation with the control filter modules
Reflective Memory Network
- What is the temporary configuration ?
- What is the final configuration ?
Simulated Plant for Green locking
- Concept
- Model construction