== Major Missions == . {*} Complete damping of the vertex suspensions . {*} Make the Reflective Memory Network work . {*} Simulated plant for Green locking [[BR]] [[BR]] ---------------- = PLANS = == TO DO LIST == || attachment:green.png '''complete'''|| attachment:orange.png '''intermediate state ''' || attachment:red.png '''incomplete''' || attachment:black.png gave up|| . ''' Binary Output working on c1sus (Alex/Joe) 1-2 days ''' . attachment:orange.png test all the BO channels and their assignments . attachment:red.png Switching over cabling from the current XY220's to the new system . ''' Complete suspension damping keeping in mind Version B coils. (1-2 days?) ''' . attachment:green.png damping all the vertex suspensions with the new CDS . attachment:red.png check if the binary outputs are working . ''' Get RFM working! (We have new parts and need new IPC parser) (3-4 days) ''' . attachment:green.png string the RFM optical fiber connecting C1SUS and C1ISCEX . attachment:orange.png install PCI-5565 driver on c1sus . attachment:red.png install PCI-5565 driver on c1iscex . attachment:red.png test the RFM card by running the diagnostic script on the individually . attachment:red.png test the RFM with the epics . ''' Get both end stations working ''' . attachment:red.png Check we have correct number of cables (againi tomorrow). . attachment:red.png Check if both end stations are correctly running . ''' Get IOO front end machine working ''' . attachment:red.png Get thing computer into 1X1 or 1X2 rack . attachment:red.png get IO chassis into 1X1 or 1X2 working. (5 days) . ''' Simulated Green Locking ''' . attachment:red.png conceptual design . attachment:red.png make realtime simlink model . attachment:red.png compile and install the model . ''' LSC simulated plant ''' . attachment:green.png conceptual design . attachment:green.png make realtime simlink model . attachment:orange.png compile and install the model . ''' Fix non-working IO chassis ''' . attachment:red.png Check on fiber with Rolf for LSC . attachment:red.png time . ''' renewal of medm screens for the vertex suspensions ''' . ''' renewal of realtime control model ''' . ''' Gentoo patch ''' . not high priority - unless they stop making backwards compatibility - do it when we have time [[BR]] [[BR]] == Wish List == (not urgent things, but somethings we want to implement at some points) . ''' channel wiki ''' . ''' wiki hyperlink on a medm screen ''' == TIME LINE SCHEDULE == . Put time line schedule here. [[BR]] [[BR]] ----------- = DETAILED CONSIDERATIONs = == Cable Requirements == . Do we have sufficient number of the cables ? . Let's doublecheck it. [[BR]] [[BR]] == Notes about Binary Outputs == . How to make a bitwise . relation with the control filter modules [[BR]] [[BR]] == Reflective Memory Network == . What is the temporary configuration ? . What is the final configuration ? [[BR]] [[BR]] == Simulated Plant for Green locking == . Concept . Model construction [[BR]] [[BR]] |
September CDS plan
Major Missions
Complete damping of the vertex suspensions
Make the Reflective Memory Network work
Simulated plant for Green locking
PLANS
TO DO LIST
attachment:green.png complete
attachment:orange.png intermediate state
attachment:red.png incomplete
attachment:black.png gave up
Binary Output working on c1sus (Alex/Joe) 1-2 days
- attachment:orange.png test all the BO channels and their assignments
- attachment:red.png Switching over cabling from the current XY220's to the new system
Complete suspension damping keeping in mind Version B coils. (1-2 days?)
- attachment:green.png damping all the vertex suspensions with the new CDS
- attachment:red.png check if the binary outputs are working
Get RFM working! (We have new parts and need new IPC parser) (3-4 days)
- attachment:green.png string the RFM optical fiber connecting C1SUS and C1ISCEX
- attachment:orange.png install PCI-5565 driver on c1sus
- attachment:red.png install PCI-5565 driver on c1iscex
- attachment:red.png test the RFM card by running the diagnostic script on the individually
- attachment:red.png test the RFM with the epics
Get both end stations working
- attachment:red.png Check we have correct number of cables (againi tomorrow).
- attachment:red.png Check if both end stations are correctly running
Get IOO front end machine working
- attachment:red.png Get thing computer into 1X1 or 1X2 rack
- attachment:red.png get IO chassis into 1X1 or 1X2 working. (5 days)
Simulated Green Locking
- attachment:red.png conceptual design
- attachment:red.png make realtime simlink model
- attachment:red.png compile and install the model
LSC simulated plant
- attachment:green.png conceptual design
- attachment:green.png make realtime simlink model
- attachment:orange.png compile and install the model
Fix non-working IO chassis
- attachment:red.png Check on fiber with Rolf for LSC
- attachment:red.png time
renewal of medm screens for the vertex suspensions
renewal of realtime control model
Gentoo patch
- not high priority - unless they stop making backwards compatibility - do it when we have time
Wish List
(not urgent things, but somethings we want to implement at some points)
channel wiki
wiki hyperlink on a medm screen
TIME LINE SCHEDULE
- Put time line schedule here.
DETAILED CONSIDERATIONs
Cable Requirements
- Do we have sufficient number of the cables ?
- Let's doublecheck it.
Notes about Binary Outputs
- How to make a bitwise
- relation with the control filter modules
Reflective Memory Network
- What is the temporary configuration ?
- What is the final configuration ?
Simulated Plant for Green locking
- Concept
- Model construction