Stage 1

Hardware

Software

Stage 2

Software

Job (Who needs to do it)

Estimated Time to Do

6/7-6/11

6/14-6/18

6/21-6/25

6/28-7/2

7/5-7/9

7/12-7/16

719-7/23

7/26-7/30

Make space in 1Y2 and 1X3 for new IOO chassis (Joe/Steve/Input from Rana?)

3 days

Planned

Install IO chassis/Computers/DAQ router (Joe/Alex/Steve)

1 Week

Planned (SUS)

Planned (LSC, South End)

Planned (IO)

Run ethernet for DAQ, Run fiber for timing board to ends, Run Dolphin cables for LSC (Joe/?)

1 day

Planned

Get IOP processor code working (Alex/Rolf)

1 week ??

Get IOP processor code to handle switch from real to sim plant (Alex/Rolf)

1 week-1 month??

Make Filter Matrix part (Joe/Alex)

2 days

Done

Get AA filters, (de)whitening filters (Joe)

1 day

Done

Make script to populate filters (Joe)

2 days

Done

Make medm screens (Joe)

3 days

In Progress

Add noise generators to all models (Joe)

2 days

Planned

Fix Binary Output handling in plants (Joe)

1 week

Planned

Test full LSC/LSP with vertex/end suspensions (Joe)

1 week

Planned

Build IO controller/plant models (Joe)

2 days

Planned

Test full LSC/LSP with IO and vertex/end suspensions (Joe)

3 days

Planned

Add green locking/add green locking plant (Joe/Kiwamu)

1 week

Planned

Prepare ADC/DAC interface for green locking (kiwamu)

1 week?

Planned

Test green controls/simulated plant (Joe/Kiwamu)

3 days

Planned

Convert to actual ADCs/DAC/BIO inputs (Joe)

2 days

Planned

CDS/Action_items_for_CDS_upgrade (last edited 2012-01-03 23:02:37 by localhost)