Action Item List

<<TableOfContents: execution failed [Argument "maxdepth" must be an integer value, not "[0]"] (see also the log)>>



Indicators

green.png complete

orange.png intermediate state

red.png nothing happened

black.png gave up



X end table arrangement

status

items

notes

green.png

measurement of lasers' PZT responses

Advanced_Techniques/Green_Locking/Lasers

green.png

NPRO placement / optical assembly at the end

-

green.png

SHG at the end table

-

green.png

Control system placement

-

green.png

Coarse/fine alignment to the cavity

-

green.png

Lock of the green beam to the cavity

-

green.png

temperature settings for the doubling crystal

-

orange.png

optimization of mode matching

-

green.png

noise characterization of the RFPD

-



X arm locking

status

items

notes

green.png

lock the laser to the X arm with a dichroic ETM

-

green.png

align X arm to the IR beam, and make it flashing

-

green.png

lock the cavity to the IR (or lock the IR to the cavity)

-

green.png

A2L to precisely adjust the spot positions for both IR and green.

-

green.png

overlap IR and green path

-

green.png

digital control to stabilize X arm

-

orange.png

noise budget

-



Y end table arrangement

status

items

notes

green.png

set up the optics, laser, doubling crystal and electronics

-

green.png

lock the laser to the Y arm with a dichroic ETM

-



Y arm locking



PSL table arrangement

status

items

notes

green.png

mode matching to the crystal

-

green.png

SHG at the PSL table

-

green.png

rearrangement of the set up due to the PSL upgrade

-

green.png

temperature setting for the doubling crystal

-

green.png

preparation of the RFPD

-

green.png

noise characterization of the RFPD

-



Digital control

status

items

notes

orange.png

conceptual design of simulated plant

-

green.png

make a realtime control model

-

red.png

make a simulated plant model

-

orange.png

GPIB interfaces or RS232 interface to control the crystal temperature

-

red.png

measure ADC/DAC noise with the new CDS system

-

orange.png

measure time delay of the new CDS systems

-

green.png

get RFM working

-

red.png

Think about how we use binary outputs ?

-

green.png

make a slow temperature controller

-

orange.png

string cables to ADCs and DACs

done only X end

orange.png

medm screens

done only X end



Analog electronics

status

items

notes

red.png

measure/calculate the requirements for the whitening filter

/!\ needs to be done soon

red.png

build and install the whitening filters

-

green.png

modification of the PDH boxes

-

green.png

characterization of the PDH box

-

green.png

order some electronic racks dedicated for green locking

-

green.png

make a summing cricuit with BW of ~200kHz

-

green.png

characterization of the VCO box

need a summary

red.png

buy one more frequency counter for the other arm

-

red.png

make power cables for the corner setup

-

red.png

make a dedicated beanote detection circuit board

-



Vertex tank optical arrangement

status

items

notes

green.png

In-vac steering (PO transmission / Periscope / Mirrors)

-

red.png

order new mirrors for SR2 and PR2

-

red.png

installation of new mirrors on SR2 and PR2

-



Performance test

status

items

notes

red.png

ADC/DAC noise measurement

-

red.png

evaluations of the PDH end locking

-

red.png

Frequency discriminator noise

-

red.png

circuit noise

-

red.png

estimate the performance from a simulation (or any calculation)

/!\ Needs to be done soon

red.png

f_noise of green beam

-

red.png

Relative f_noise between the PSL green and the Arm transmitted green ALS performance

-



Sophistication of the scheme

status

items

notes

red.png

Automatic handing off scripts

-

red.png

Ready-to-go panels for AdvLIGO

-

red.png

green coated vacuum chamber's windows

-

red.png

dichroic CCD cameras

-

red.png

Automatic alignment of the green beam

needs a PZT steering mirrors and WFSs

red.png

Green Michelson for precise ETM calibration

optional

red.png

Absolute length / mode spacing measurement by green

optional



misc

status

items

notes

green.png

recheck order list

-

green.png

reorder some of stuff

-

orange.png

check the item we have

-

green.png

check polarization of the doubling crystal

-

orange.png

optimize the damping control of each optic

-

Advanced_Techniques/Green_Locking/action_item_list (last edited 2012-01-03 23:02:41 by localhost)