A more [[Detailed Vent Plan|detailed]] plan is [[Detailed Vent Plan|here]] ## page was renamed from Plan of Action
Line 3: Line 3:
== [[In vacuum pictures]] == ------
We vented from 9/19/06 through 10/5/06 to install the DC readout in-vacuum beamline
and adjust suspension OSEMs. The following were the plans we assembled
prior to the vent. Everything proceeded more-or-less according to plan,
but please see the ilog for details.
Line 5: Line 9:
General:  VacVentPicturesOct2006
Line 7: Line 11:
 1. Implement DC readout at the 40m
 1. Detect Gravitational Waves
------
Line 11: Line 14:

[[Detailed Vent Plan]]


We vented from 9/19/06 through 10/5/06 to install the DC readout in-vacuum beamline and adjust suspension OSEMs. The following were the plans we assembled prior to the vent. Everything proceeded more-or-less according to plan, but please see the ilog for details.


Rough Schedule

Detailed Vent Plan

In-vacuum tasks

DC readout requirements

Additional in-vacuum requirements

Triggers for breaking vacuum

In Air Pre-Alignment

OSEM adjustment proceedure

Misc In Vac Work