Size: 329
Comment:
|
Size: 594
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 1: | Line 1: |
| A more [[Detailed Vent Plan|detailed]] plan is coming soon. | ## page was renamed from Plan of Action |
| Line 3: | Line 3: |
| General: | ------ We vented from 9/19/06 through 10/5/06 to install the DC readout in-vacuum beamline and adjust suspension OSEMs. The following were the plans we assembled prior to the vent. Everything proceeded more-or-less according to plan, but please see the ilog for details. |
| Line 5: | Line 9: |
| 1. Implement DC readout at the 40m 1. Detect Gravitational Waves |
VacVentPicturesOct2006 ------ |
| Line 9: | Line 14: |
[[Detailed Vent Plan]] |
|
| Line 20: | Line 27: |
| [[OSEM adjustment proceedure]] |
We vented from 9/19/06 through 10/5/06 to install the DC readout in-vacuum beamline and adjust suspension OSEMs. The following were the plans we assembled prior to the vent. Everything proceeded more-or-less according to plan, but please see the ilog for details.