Upgrade of the 40m

Events

  • Dec 21, 2010: ETMX/Y installation, In-Vac installation finished, evacuation

  • Nov 3, 2010: Slow green beat note control

  • Oct 22, 2010: First green beat note found

  • Oct 5, 2010: X-End green beam reahed to the PSL table

  • Sep 27, 2010: 3rd Vent

  • Sep 20, 2010: CDS switch over to the new system

  • Sep -17, 2010: PSL upgrade initial work done

  • Aug 26-, 2010: PSL upgrade initial work

  • Aug 5-25, 2010: PSL table upgrade

  • Aug 1, 2010: Back to Vacuum

  • Jul 20, 2010: 2nd Vent

  • Jun 18, 2010: Input MMT installation and measurement completed

  • May 27, 2010: First Green Locking of the arm

  • Apr 23, 2010: First SHG light at the 40m for this upgrade

  • Apr 13, 2010: PRM/SRM removal form the table

  • Apr 12, 2010: ITMX SOS installation completed

  • Apr 6, 2010: ITMY SOS installation completed

  • Mar 2, 2010: Vent

  • Feb 20, 2010: Power supply stop

  • Jan 28, 2010: TAC meeting Jan 2010

  • Dec 7-11, 2009: Vent for test mass cleaning

  • Nov 12-17, 2009: ETMY CDS test