Differences between revisions 82 and 86 (spanning 4 versions)
Revision 82 as of 2010-08-07 01:32:55
Size: 2617
Editor: KojiArai
Comment:
Revision 86 as of 2010-09-10 14:38:03
Size: 2754
Comment:
Deletions are marked like this. Additions are marked like this.
Line 4: Line 4:
 * [[Upgrade 09/IFO_Modeling|Upgrade IFO Modeling]]
Line 20: Line 21:
   * [[Upgrade 09/PSL|PSL Table Lifting]]    * [[Upgrade 09/PSL Table Lifting|PSL Table Lifting]]
Line 24: Line 25:
   * [[Upgrade 09/CDS/September CDS plan|CDS test plan for September]]

Upgrade of the 40m

Events

  • July 20, 2010: 2nd Vent

  • June 18, 2010: Input MMT installation and measurement completed

  • May 27, 2010: First Green Locking of the arm

  • Apr 23, 2010: First SHG light at the 40m for this upgrade

  • Apr 13, 2010: PRM/SRM removal form the table

  • Apr 12, 2010: ITMX SOS installation completed

  • Apr 6, 2010: ITMY SOS installation completed

  • Mar 2, 2010: Vent

  • Feb 20, 2010: Power supply stop

  • Jan 28, 2010: TAC meeting Jan 2010

  • Dec 7-11, 2009: Vent for test mass cleaning

  • Nov 12-17, 2009: ETMY CDS test