Line 24: Line 24:
 * '''May 2X, 2010:''' First Green Locking of the arm  * '''July 20, 2010:''' [[Vent Jul 2010|2nd Vent]]
 * '''June 18, 2010:''' Input MMT installation and measurement completed
 * '''May 27, 2010:''' First Green Locking of the arm

Upgrade of the 40m

Events

  • July 20, 2010: 2nd Vent

  • June 18, 2010: Input MMT installation and measurement completed

  • May 27, 2010: First Green Locking of the arm

  • Apr 23, 2010: First SHG light at the 40m for this upgrade

  • Apr 13, 2010: PRM/SRM removal form the table

  • Apr 12, 2010: ITMX SOS installation completed

  • Apr 6, 2010: ITMY SOS installation completed

  • Mar 2, 2010: Vent

  • Feb 20, 2010: Power supply stop

  • Jan 28, 2010: TAC meeting Jan 2010

  • Dec 7-11, 2009: Vent for test mass cleaning

  • Nov 12-17, 2009: ETMY CDS test