|
Size: 329
Comment:
|
← Revision 23 as of 2012-01-03 23:03:06 ⇥
Size: 3298
Comment: converted to 1.6 markup
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 1: | Line 1: |
| <<TableOfContents(2)>> | <<TableOfContents(3)>> |
| Line 7: | Line 7: |
| - We are going to lift the table by | * The PSL table height will be raised to the level of the AP table. * This will be done using 6 TMC's Rigid Damped Tripod legs. * The legs will be grouted to the floor with concrete. |
| Line 9: | Line 11: |
| - The PSL table height will be raised to the level of the AP table. - This will be done using 6 TMC's Rigid Damped Tripod legs. - The legs will be grouted to the floor with concrete. |
== Drawing for the leg positions == |
| Line 13: | Line 13: |
| == | - The planned positions of the legs are shown below. |
| Line 15: | Line 15: |
| - Their planned positions shown below. | [[Upgrade 09/PSL Table Lifting|{{attachment:psllegs.png||width=400}}]] == Work schedule == {{attachment:PSL_work_schedule.png}} [[attachment:PSL_work_schedule.pdf]] == Cable Removal == [[attachment:PSL_cable_map.pdf]] == Work Log == === Aug 5th === 10am-4pm?: (Kiwamu, Alberto, Koji) * Removing the unused cables around the PSL table and the control room === Aug 6th === 10am-5pm: (Steve, Jenne, Alberto, Kiwamu, Koji) * We labeled the cables to be disconnected * These will be disconnected in order to isolate the PSL table and the frame (housing) from the other part of the lab. * Upon the labeling we made the list and the map of the cables to be removed. * On Monday we disconnect those cables one by one accoding to the list. * The following stuffs have been removed from the PSL table * The big nuts at the side of the PSL table * The cable ties on the PSL frame * Innolight 2W * The green pickoff optics at the edge * The optics on the shelf * The oscilloscopes on the shelf * The OMC power supply cable was visited. * The connections to the power supply were removed. There are two HV outputs. * We put thick and long optical poles * They are placed at the edge of the table so that we can put the plastic sheets on the table without touching the optics. === Aug 9th === 9am-5pm: (Steve, Jenne, Alberto, Koji) * Disconnecting the cables ==> All * Shutting down the PSL ==> Steve/Koji o Draining the cooling water ==> Steve * Removals o The accelerometers ==> Jenne o The reference cavity chamber ==> Steve o The small periscope ==> Alberto * Sealing of the table with the plastic sheets * The chiller is planned to go to MIT === Aug 10th === 10am-2pm: (Steve, Mike, Koji) * Lifting of the PSL frame * Lifting of the PSL table * Putting Al legs and tie them to the frame bars with steel hose clamps * Attach the template board to the bottom surface of the PSL table with the C-clamps === Aug 11th === 9am-12pm: (Steve, Caltech Carpentar) * Drilling and tapping of the eighteen 1/4-20 holes to the bottom surface of the table 3:30pm-4:30pm: (Katharine, Sharmila, Gopal, Kiwamu, Jenne, Aidan, Steve, and Koji) * Wrapping up the central part of the interferometer with plastic sheets === Aug 12th === 9am-2pm: (Steve, Bertin Bros. Construction, Inc) * Powered down 1Y1 and 1Y2 instrument racks of MC and RF-systems * Covers the both racks, the SP table with plastics. * Bertin Bros. Construction, Inc worked on the floor preparation. (The head man: Robby Bertin, cell 626.831.2264) * removed tiles * cleaned off tile glue, * drilled for ribbed steel bars * roughed clean-surface for good bounding. * painted floor with bounding agent |
Contents
PSL Table Lifting
Overview
- The PSL table height will be raised to the level of the AP table.
- This will be done using 6 TMC's Rigid Damped Tripod legs.
- The legs will be grouted to the floor with concrete.
Drawing for the leg positions
- The planned positions of the legs are shown below.
Work schedule
Cable Removal
Work Log
Aug 5th
10am-4pm?: (Kiwamu, Alberto, Koji)
- Removing the unused cables around the PSL table and the control room
Aug 6th
10am-5pm: (Steve, Jenne, Alberto, Kiwamu, Koji)
- We labeled the cables to be disconnected
- These will be disconnected in order to isolate the PSL table and the frame (housing) from the other part of the lab.
- Upon the labeling we made the list and the map of the cables to be removed.
- On Monday we disconnect those cables one by one accoding to the list.
- The following stuffs have been removed from the PSL table
- The big nuts at the side of the PSL table
- The cable ties on the PSL frame
- Innolight 2W
- The green pickoff optics at the edge
- The optics on the shelf
- The oscilloscopes on the shelf
- The OMC power supply cable was visited.
- The connections to the power supply were removed. There are two HV outputs.
- We put thick and long optical poles
- They are placed at the edge of the table so that we can put the plastic sheets on the table without touching the optics.
Aug 9th
9am-5pm: (Steve, Jenne, Alberto, Koji)
Disconnecting the cables ==> All
Shutting down the PSL ==> Steve/Koji
o Draining the cooling water ==> Steve
- Removals
o The accelerometers ==> Jenne o The reference cavity chamber ==> Steve o The small periscope ==> Alberto
- Sealing of the table with the plastic sheets
- The chiller is planned to go to MIT
Aug 10th
10am-2pm: (Steve, Mike, Koji)
- Lifting of the PSL frame
- Lifting of the PSL table
- Putting Al legs and tie them to the frame bars with steel hose clamps
- Attach the template board to the bottom surface of the PSL table with the C-clamps
Aug 11th
9am-12pm: (Steve, Caltech Carpentar)
- Drilling and tapping of the eighteen 1/4-20 holes to the bottom surface of the table
3:30pm-4:30pm: (Katharine, Sharmila, Gopal, Kiwamu, Jenne, Aidan, Steve, and Koji)
- Wrapping up the central part of the interferometer with plastic sheets
Aug 12th
9am-2pm: (Steve, Bertin Bros. Construction, Inc)
- Powered down 1Y1 and 1Y2 instrument racks of MC and RF-systems
- Covers the both racks, the SP table with plastics.
- Bertin Bros. Construction, Inc worked on the floor preparation. (The head man: Robby Bertin, cell 626.831.2264)
- removed tiles
- cleaned off tile glue,
- drilled for ribbed steel bars
- roughed clean-surface for good bounding.
- painted floor with bounding agent

