PSL Table Lifting

Overview

  • The PSL table height will be raised to the level of the AP table.
  • This will be done using 6 TMC's Rigid Damped Tripod legs.
  • The legs will be grouted to the floor with concrete.

Drawing for the leg positions

- The planned positions of the legs are shown below.

psllegs.png

Work schedule

attachment:PSL_work_schedule.png attachment:PSL_work_schedule.pdf

Cable Removal

attachment:PSL_cable_map.pdf

Work Log

Aug 5th

10am-4pm?: (Kiwamu, Alberto, Koji)

  • Removing the unused cables around the PSL table and the control room

Aug 6th

10am-5pm: (Steve, Jenne, Alberto, Kiwamu, Koji)

  • We labeled the cables to be disconnected
    • These will be disconnected in order to isolate the PSL table and the frame (housing) from the other part of the lab.
    • Upon the labeling we made the list and the map of the cables to be removed.
    • On Monday we disconnect those cables one by one accoding to the list.
  • The following stuffs have been removed from the PSL table
    • The big nuts at the side of the PSL table
    • The cable ties on the PSL frame
    • Innolight 2W
    • The green pickoff optics at the edge
    • The optics on the shelf
    • The oscilloscopes on the shelf
  • The OMC power supply cable was visited.
    • The connections to the power supply were removed. There are two HV outputs.
  • We put thick and long optical poles
    • They are placed at the edge of the table so that we can put the plastic sheets on the table without touching the optics.

Aug 9th

9am-5pm: (Steve, Jenne, Alberto, Koji)

  • Disconnecting the cables ==> All

  • Shutting down the PSL ==> Steve/Koji

    • o Draining the cooling water ==> Steve

  • Removals
    • o The accelerometers ==> Jenne o The reference cavity chamber ==> Steve o The small periscope ==> Alberto

  • Sealing of the table with the plastic sheets
  • The chiller is planned to go to MIT