There will be a power shutdown for 40m lab completely on Feb 5th (Sat), 2022 from 10am to 2pm. Following is the detailed plan for how to shutdown the whole lab and bring it back up online. == Shutdown == === CDS Shutdown === ==== Creating backups ==== * Ensure all SDF tables in all FE models are saved to keep the changes persistent through power cycle. * Note that ADC, DAC index orders might change in C1SUS2 I/O chassis and maybe others. * Create burtgooey backups of all available req files or ensure that autoburt has successfully run in past some time. ==== Slow computers ==== |