== July 2010 Meeting of the 40m Technical Advisory Committee ==
[[attachment:TAC_2010_Jul.pdf]]
[[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=13490|TAC Slides in the DCC]]
July 15th, 2010 <
> 9:00 AM PDT <
> Call in instructions:<
> (866) 380 - 5536<
> International: (816) 249 - 4731<
> Code: 6263958709<
>
--------
I. '''Agenda'''
I. Current Status / Recent Work B. Upgrade Plans
II. '''Recent Status'''
A. Personnel Changes
1. Rob Ward: 1/2004 - 3/2010 (gone to Paris - APC / Barsuglia)
1. [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=9237|Rob's Thesis]]
III. '''Upgrade'''
A. Purpose of the upgrade
1. AdvLIGO LSC / AdVLIGO testbed (green/CDS)
1. Advanced techniques
A. Current status of the upgrade preparation
1. Mechanics -
* Done: SOSs for new, light test masses
* Done: TT suspensions for PRC
* ANU tip/tilt: LLO Blades + TAMA/ANU compliant eddy current damping
* Done: In-vac mounts for green
* To be done: Supplimental parts for TTs, some in-vac mechanics
1. Optics
* Done: Have the SRM / ITMs (dichroic). PRMs polished - coating waits for arm loss measurement
* Done: optical layout
* MMT design (Jenne): histograms, alignment orthogonality
* Optics - Gooch & Housego magic HR
* Done: smaller aux optics, folding mirrors (G&H), and green mirrors, all in hand
* In progress: ETMs are being polished / coated. ETD = September
1. Electronics (RF system)
* Done: Designed the multiple frequency RF system to preserve the phase noise performance of the oscillator
* RF signal distribution (oscillators, splitters, amplifiers, etc.)
* Triple-Resonant EOM (New Focus KTP + resonant circuit)
* 5 of 10 PDs tuned, characterized and made shot noise limited
* To be done: Finish the remaining 5 PDs / Install the photodiodes on the tables
1. Green beam injection (unstabilized fiber + green injection from the ends)
* Done: End table constructed / fringe lock achieved
1. CDS -
* Done: Demonstrated the control system of one suspension including the cavity lock.
* Layout diagram
* 90% of H/Ws at the 40m
* To be done: Integration of the system
* Local control tests
* Integration tests
1. PSL laser/table upgrade
A. Upgrade Plans
1. upgrading order and rough schedule
IV. End
--------