Differences between revisions 7 and 8
Revision 7 as of 2013-04-03 18:23:37
Size: 1192
Comment:
Revision 8 as of 2013-04-03 18:54:22
Size: 1568
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
== PR/DR MI commissioning == == PRMI commissioning ==
Line 10: Line 10:
 * Lower Q on Vio2 filters
Line 11: Line 12:
 * Finish updating IFO configure scripts (Jamie)  * Finish updating IFO configure scripts, medm "restore" (Jamie)
Line 31: Line 32:
== DRMI ==

This and FPMI are the next primary tasks. '''''We will need to vent to flip SR2 first.'''''

 * SRC mirror RoC calculations. What is the long-term solution? (Jamie)
Line 33: Line 40:
[[endtable_upgrade|Project page]].
 * ETMY table must be completed ASAP
This is needed before we move on the FPMI commissioning.

 *
[[endtable_upgrade|Project page]]

 * ETMY table must be completed ASAP (Manasa)
Line 40: Line 50:

We obviously need both end tables fully functional before we get to this.

40m work plan

This should be kept up-to-date. This is an overview of our near-term goals. We can link to other TODO lists from here.

PRMI commissioning

  • PRMI locked!
  • Investigate triggering (trigger on POP110 instead?)
  • What is the correct normalization?
  • Lower Q on Vio2 filters
  • Finish updating IFO configure scripts, medm "restore" (Jamie)
  • OSA modulation depth measurements at:
    • REFL
    • AS
  • Power budget at all available ports, include 1f(22)/2f(110)
    • PRC gain
  • Oplev calibration (BS? PRM?)
  • Sensing matrix
  • Cavity length (use new Anamaria method)
  • Loop gain (make sure loop is stable for measurements)
  • Noise budget
  • Full Finesse model.
  • Fix hardware anti-aliasing in LSC (move up cutoff freq to correspond to sample rate)

DRMI

This and FPMI are the next primary tasks. We will need to vent to flip SR2 first.

  • SRC mirror RoC calculations. What is the long-term solution? (Jamie)

End table upgrade

This is needed before we move on the FPMI commissioning.

  • Project page

  • ETMY table must be completed ASAP (Manasa)
    • What is left to do?
  • ETMX upgrade needs to be planned/coordinated.

FPMI

We obviously need both end tables fully functional before we get to this.

PRFPMI

DRFPMI

Next vent

Will need to vent soon to flip SR2.

  • SR2 flip
  • Are all black glass beam dumps installed?

Longer term:

  • New OSEM mount screws
  • New periscope plate