Differences between revisions 6 and 8 (spanning 2 versions)
Revision 6 as of 2013-01-15 00:36:33
Size: 1651
Comment:
Revision 8 as of 2013-04-03 18:54:22
Size: 1568
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
== Finishing in-vac work ==
We need to try to get this finished by the END OF THIS WEEK (1/18/2013).
== PRMI commissioning ==
Line 8: Line 7:
 * Finish TT installation
 * Recover full alignment
 * Lock PRC
 * Extract sensor card, allen key, ants from chamber before closing
 * PRMI locked!
 * Investigate triggering (trigger on POP110 instead?)
 * What is the correct normalization?
 * Lower Q on Vio2 filters
Line 13: Line 12:
== PR/DR MI commissioning ==
This is primary goal. We need to have this working by the end of the
month (1/13).
 * Finish updating IFO configure scripts, medm "restore" (Jamie)
Line 17: Line 14:
 * Lock both arms and optimally align
   * Center spots on the ITMs
 * Lock the PRMI
 * PRMI measurements:
 * OSA modulation depth measurements at:
   * REFL
   * AS
Line 22: Line 18:
   * Good camera images:
     * REFL
     * AS
     * POP - improve this camera. Expand the beam, and adjust the brightness
     * PR/BS face - get these hooked up
 * Power budget at all available ports, include 1f(22)/2f(110)
   * PRC gain
Line 28: Line 21:
   * OSA
     * REFL
     * AS
 * Oplev calibration (BS? PRM?)
Line 32: Line 23:
   * Power budget at all available ports, include 1f(22)/2f(110)
     * PRC gain

  
* Sensing matrix
   * Cavity length (use new Anamaria method)
   * Loop gain (make sure loop is stable for measurements)
   * Noise budget
 * Sensing matrix
 * Cavity length (use new Anamaria method)
 * Loop gain (make sure loop is stable for measurements)
 * Noise budget
Line 44: Line 32:
== Full IFO Locking == == DRMI ==
Line 46: Line 34:
Roughly three months. This and FPMI are the next primary tasks. '''''We will need to vent to flip SR2 first.'''''

 * SRC mirror RoC calculations. What is the long-term solution? (Jamie)
Line 50: Line 40:
[[endtable_upgrade|Project page]].
On best-effort basis, although we'll need to coordinate exactly when we
do the end-table swap out.
This is needed before we move on the FPMI commissioning.
Line 54: Line 42:
== Things to prepare for next vent ==  * [[endtable_upgrade|Project page]]
Line 56: Line 44:
We have no immediate plan to vent in the near future, but I'm going to
be checking on progress of this stuff weekly:
 * ETMY table must be completed ASAP (Manasa)
   * What is left to do?
Line 59: Line 47:
 * New TT risers
 * Black glass beam dumps
 * ETMX upgrade needs to be planned/coordinated.

== FPMI ==

We obviously need both end tables fully functional before we get to this.

== PRFPMI ==

== DRFPMI ==

== Next vent ==

Will need to vent soon to flip SR2.

 * SR2 flip
 * Are all black glass beam dumps installed?

Longer term:

40m work plan

This should be kept up-to-date. This is an overview of our near-term goals. We can link to other TODO lists from here.

PRMI commissioning

  • PRMI locked!
  • Investigate triggering (trigger on POP110 instead?)
  • What is the correct normalization?
  • Lower Q on Vio2 filters
  • Finish updating IFO configure scripts, medm "restore" (Jamie)
  • OSA modulation depth measurements at:
    • REFL
    • AS
  • Power budget at all available ports, include 1f(22)/2f(110)
    • PRC gain
  • Oplev calibration (BS? PRM?)
  • Sensing matrix
  • Cavity length (use new Anamaria method)
  • Loop gain (make sure loop is stable for measurements)
  • Noise budget
  • Full Finesse model.
  • Fix hardware anti-aliasing in LSC (move up cutoff freq to correspond to sample rate)

DRMI

This and FPMI are the next primary tasks. We will need to vent to flip SR2 first.

  • SRC mirror RoC calculations. What is the long-term solution? (Jamie)

End table upgrade

This is needed before we move on the FPMI commissioning.

  • Project page

  • ETMY table must be completed ASAP (Manasa)
    • What is left to do?
  • ETMX upgrade needs to be planned/coordinated.

FPMI

We obviously need both end tables fully functional before we get to this.

PRFPMI

DRFPMI

Next vent

Will need to vent soon to flip SR2.

  • SR2 flip
  • Are all black glass beam dumps installed?

Longer term:

  • New OSEM mount screws
  • New periscope plate