= 40m work plan = This should be kept up-to-date. This is an overview of our near-term goals. We can link to other TODO lists from here. == PR/DR MI commissioning == * PRMI locked! * Investigate triggering (trigger on POP110 instead?) * What is the correct normalization? * Finish updating IFO configure scripts (Jamie) * OSA modulation depth measurements at: * REFL * AS * Power budget at all available ports, include 1f(22)/2f(110) * PRC gain * Oplev calibration (BS? PRM?) * Sensing matrix * Cavity length (use new Anamaria method) * Loop gain (make sure loop is stable for measurements) * Noise budget * Full Finesse model. * Fix hardware anti-aliasing in LSC (move up cutoff freq to correspond to sample rate) == End table upgrade == [[endtable_upgrade|Project page]]. * ETMY table must be completed ASAP * What is left to do? * ETMX upgrade needs to be planned/coordinated. == FPMI == == PRFPMI == == DRFPMI == == Next vent == Will need to vent soon to flip SR2. * SR2 flip * Are all black glass beam dumps installed? Longer term: * New OSEM mount screws * New periscope plate |
40m work plan
This should be kept up-to-date. This is an overview of our near-term goals. We can link to other TODO lists from here.
PR/DR MI commissioning
- PRMI locked!
- Investigate triggering (trigger on POP110 instead?)
- What is the correct normalization?
- Finish updating IFO configure scripts (Jamie)
- OSA modulation depth measurements at:
- REFL
- AS
- Power budget at all available ports, include 1f(22)/2f(110)
- PRC gain
- Oplev calibration (BS? PRM?)
- Sensing matrix
- Cavity length (use new Anamaria method)
- Loop gain (make sure loop is stable for measurements)
- Noise budget
- Full Finesse model.
- Fix hardware anti-aliasing in LSC (move up cutoff freq to correspond to sample rate)
End table upgrade
- ETMY table must be completed ASAP
- What is left to do?
- ETMX upgrade needs to be planned/coordinated.
FPMI
PRFPMI
DRFPMI
Next vent
Will need to vent soon to flip SR2.
- SR2 flip
- Are all black glass beam dumps installed?
Longer term:
- New OSEM mount screws
- New periscope plate