== Interferometer work ==
Line 38: Line 40:

=== Week of 3/15-3/19 ===
 * '''3/15-18 LVC meeting''' http://www.ligo.org/conferences/lv0310/
 * '''3/19 aLIGO ISC'''

=== 4/5 ITMX/ITMY placement ===
=== 4/6 ITMY aligned ===
=== 4/12 ITMX aligned ===

== Suspension preparation ==

 * '''2/16-26 Small Optics Suspension'''
  * Wed 17 Feb
   * '''Gluing test'''
    * Epoxy test. Try gluing a dumbbell to an optic. Check strength of bond. (It's good)
  * Thurs 18 Feb
   * '''ITMX guiderod gluing'''
    * Place ITMX in guiderod fixture
    * Epoxy guiderod & standoff to ITMX (Afternoon)
    * Cure epoxy (overnight)
  * Fri 19 Feb
   * '''Magnet-dumbbell gluing'''
    * Make up matching sets of magnets using gaussmeter (Morning)
    * Etch magnets and dumbbells using razor blade (Morning)
    * Epoxy magnets to dumbbells (Morning)
    * Cure epoxy (overnight)
   * '''ITMY guiderod gluing'''
    * Place ITMY in guiderod fixtrue
    * Epoxy guiderods to ITMY (Afternoon)
    * Cure epoxy (overnight)
  * Sat 20 Feb
   * No Electricity - No work
  * Sun 21 Feb
  * Mon 22 Feb
   * '''ITMX magnet gluing'''
    * Remove ITMX from guiderod fixture, place in magnet fixture
    * Epoxy magnets ITMX (Afternoon)
    * Cure epoxy (overnight)
   * '''EQ stop preparation'''
    * Talk to Zach - help him get started on this
    * Plan for viton cutting (something to help measure / keep the razor straight while cutting)
    * Cut the Viton
    * Assemble EQ stops (stick the viton in the screws)
  * Tues 23 Feb
   * '''EQ stop preparation'''
    * Zach finish making EQ stops (at least enough for the ITMs...can finish the rest later in the week)
   * '''Hanging preparation'''
    * Balance Optical Table (Morning)
    * Make HeNe OpLev (Morning)
    * Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
   * '''ITMY magnet gluing'''
    * Glue magnets to ITMY (Afternoon)
    * Cure epoxy (overnight)

  * Tue 2 Mar ('''actual date''')
   * '''ITMX hanging'''
    * Hang and balance ITMX. (All Day)
    * Epoxy wire standoffs in place after balancing
    * Cure epoxy (overnight)

  * Tue 11 Mar ('''actual date''')
   * '''ITMY hanging'''
    * Hang and balance ITMY. (All Day)
    * Epoxy wire standoffs in place after balancing
    * Cure epoxy (overnight)

  * Mon 22 Mar ('''actual date''')
   * '''ITMX/ITMY baking''' - done
    * Remove both ITMs from their suspensions (Morning) 2 person job
    * Vacuum bake to clean the optics - 48 hours
    * Leave the 2 ITMs alone in the bake oven
    * Get RGA scan to confirm they're sparkly clean

  * Mon 5 Apr ('''actual date''')
   * '''Final Prep for Installation'''
    * Reinstall optics in suspensions (Definitely a 2 person job)
    * Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs)

Return to Planning page

Interferometer work

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/18 Power shutdown preparation

  • 2/19 No work / only papers and pens

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 Reserved for trouble shooting

  • 2/23 or 24 Vent

  • 2/24 40m meeting

  • 2/25 Tank opening

    • OMC/IMC access connector
    • ITMX/Y heavy door
  • 2/25 Input MC beam adjustment

    • beam centering to MC mirrors

Week of 3/15-3/19

4/5 ITMX/ITMY placement

4/6 ITMY aligned

4/12 ITMX aligned

Suspension preparation

  • 2/16-26 Small Optics Suspension

    • Wed 17 Feb
      • Gluing test

        • Epoxy test. Try gluing a dumbbell to an optic. Check strength of bond. (It's good)
    • Thurs 18 Feb
      • ITMX guiderod gluing

        • Place ITMX in guiderod fixture
        • Epoxy guiderod & standoff to ITMX (Afternoon)

        • Cure epoxy (overnight)
    • Fri 19 Feb
      • Magnet-dumbbell gluing

        • Make up matching sets of magnets using gaussmeter (Morning)
        • Etch magnets and dumbbells using razor blade (Morning)
        • Epoxy magnets to dumbbells (Morning)
        • Cure epoxy (overnight)
      • ITMY guiderod gluing

        • Place ITMY in guiderod fixtrue
        • Epoxy guiderods to ITMY (Afternoon)
        • Cure epoxy (overnight)
    • Sat 20 Feb
      • No Electricity - No work
    • Sun 21 Feb
    • Mon 22 Feb
      • ITMX magnet gluing

        • Remove ITMX from guiderod fixture, place in magnet fixture
        • Epoxy magnets ITMX (Afternoon)
        • Cure epoxy (overnight)
      • EQ stop preparation

        • Talk to Zach - help him get started on this
        • Plan for viton cutting (something to help measure / keep the razor straight while cutting)
        • Cut the Viton
        • Assemble EQ stops (stick the viton in the screws)
    • Tues 23 Feb
      • EQ stop preparation

        • Zach finish making EQ stops (at least enough for the ITMs...can finish the rest later in the week)
      • Hanging preparation

        • Balance Optical Table (Morning)
        • Make HeNe OpLev (Morning)

        • Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
      • ITMY magnet gluing

        • Glue magnets to ITMY (Afternoon)
        • Cure epoxy (overnight)
    • Tue 2 Mar (actual date)

      • ITMX hanging

        • Hang and balance ITMX. (All Day)
        • Epoxy wire standoffs in place after balancing
        • Cure epoxy (overnight)
    • Tue 11 Mar (actual date)

      • ITMY hanging

        • Hang and balance ITMY. (All Day)
        • Epoxy wire standoffs in place after balancing
        • Cure epoxy (overnight)
    • Mon 22 Mar (actual date)

      • ITMX/ITMY baking - done

        • Remove both ITMs from their suspensions (Morning) 2 person job
        • Vacuum bake to clean the optics - 48 hours
        • Leave the 2 ITMs alone in the bake oven
        • Get RGA scan to confirm they're sparkly clean
    • Mon 5 Apr (actual date)

      • Final Prep for Installation

        • Reinstall optics in suspensions (Definitely a 2 person job)
        • Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs)