Line 1: Line 1:
[[Upgrade 09/Installation Plan|Return to Planning page]]
Line 36: Line 38:

=== Week of 3/15-3/19 ===
 * '''3/15-18 LVC meeting''' http://www.ligo.org/conferences/lv0310/
 * '''3/19 aLIGO ISC'''

=== 4/5 ITMX/ITMY placement ===
=== 4/6 ITMY aligned ===
=== 4/12 ITMX aligned ===

Return to Planning page

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/18 Power shutdown preparation

  • 2/19 No work / only papers and pens

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 Reserved for trouble shooting

  • 2/23 or 24 Vent

  • 2/24 40m meeting

  • 2/25 Tank opening

    • OMC/IMC access connector
    • ITMX/Y heavy door
  • 2/25 Input MC beam adjustment

    • beam centering to MC mirrors

Week of 3/15-3/19

4/5 ITMX/ITMY placement

4/6 ITMY aligned

4/12 ITMX aligned

Past_Plans (last edited 2012-01-03 23:02:43 by localhost)