== Interferometer work ==
Line 36: Line 39:

=== Week of 3/15-3/19 ===
 * '''3/15-18 LVC meeting''' http://www.ligo.org/conferences/lv0310/
 * '''3/19 aLIGO ISC'''
 * '''3/22 MMT Optics baking '''
 * '''3/23 MC realigned'''

=== 4/5 ITMX/ITMY placement ===
=== 4/6 ITMY aligned ===
=== 4/12 ITMX aligned ===
=== 4/13 PRM/SRM removed from the table ===
== Suspension preparation ==
 * Wed 17 Feb
  * '''Gluing test'''
   * Epoxy test. Try gluing a dumbbell to an optic. Check strength of bond. (It's good)
 * Thurs 18 Feb
  * '''ITMX guiderod gluing'''
   * Place ITMX in guiderod fixture
   * Epoxy guiderod & standoff to ITMX (Afternoon)
   * Cure epoxy (overnight)
 * Fri 19 Feb
  * '''Magnet-dumbbell gluing'''
  * Make up matching sets of magnets using gaussmeter (Morning)
  * Etch magnets and dumbbells using razor blade (Morning)
  * Epoxy magnets to dumbbells (Morning)
  * Cure epoxy (overnight)
  * '''ITMY guiderod gluing'''
   * Place ITMY in guiderod fixtrue
   * Epoxy guiderods to ITMY (Afternoon)
   * Cure epoxy (overnight)
 * Sat 20 Feb
  * No Electricity - No work
 * Sun 21 Feb
 * Mon 22 Feb
  * '''ITMX magnet gluing'''
   * Remove ITMX from guiderod fixture, place in magnet fixture
   * Epoxy magnets ITMX (Afternoon)
   * Cure epoxy (overnight)
  * '''EQ stop preparation'''
   * Talk to Zach - help him get started on this
   * Plan for viton cutting (something to help measure / keep the razor straight while cutting)
   * Cut the Viton
   * Assemble EQ stops (stick the viton in the screws)
 * Tues 23 Feb
  * '''EQ stop preparation'''
   * Zach finish making EQ stops (at least enough for the ITMs...can finish the rest later in the week)
  * '''Hanging preparation'''
   * Balance Optical Table (Morning)
   * Make HeNe OpLev (Morning)
   * Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
  * '''ITMY magnet gluing'''
   * Glue magnets to ITMY (Afternoon)
   * Cure epoxy (overnight)

 * Tue 2 Mar ('''actual date''')
  * '''ITMX hanging'''
   * Hang and balance ITMX. (All Day)
   * Epoxy wire standoffs in place after balancing
   * Cure epoxy (overnight)

 * Tue 11 Mar ('''actual date''')
  * '''ITMY hanging'''
   * Hang and balance ITMY. (All Day)
   * Epoxy wire standoffs in place after balancing
   * Cure epoxy (overnight)

 * Mon 22 Mar ('''actual date''')
  * '''ITMX/ITMY baking''' - done
   * Remove both ITMs from their suspensions (Morning) 2 person job
   * Vacuum bake to clean the optics - 48 hours
   * Leave the 2 ITMs alone in the bake oven
   * Get RGA scan to confirm they're sparkly clean

 * Mon 5 Apr ('''actual date''')
  * '''Final Prep for Installation'''
   * Reinstall optics in suspensions (Definitely a 2 person job)
   * Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs)

Return to Planning page

Interferometer work

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/18 Power shutdown preparation

  • 2/19 No work / only papers and pens

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 Reserved for trouble shooting

  • 2/23 or 24 Vent

  • 2/24 40m meeting

  • 2/25 Tank opening

    • OMC/IMC access connector
    • ITMX/Y heavy door
  • 2/25 Input MC beam adjustment

    • beam centering to MC mirrors

Week of 3/15-3/19

4/5 ITMX/ITMY placement

4/6 ITMY aligned

4/12 ITMX aligned

4/13 PRM/SRM removed from the table

Suspension preparation

  • Wed 17 Feb
    • Gluing test

      • Epoxy test. Try gluing a dumbbell to an optic. Check strength of bond. (It's good)
  • Thurs 18 Feb
    • ITMX guiderod gluing

      • Place ITMX in guiderod fixture
      • Epoxy guiderod & standoff to ITMX (Afternoon)

      • Cure epoxy (overnight)
  • Fri 19 Feb
    • Magnet-dumbbell gluing

    • Make up matching sets of magnets using gaussmeter (Morning)
    • Etch magnets and dumbbells using razor blade (Morning)
    • Epoxy magnets to dumbbells (Morning)
    • Cure epoxy (overnight)
    • ITMY guiderod gluing

      • Place ITMY in guiderod fixtrue
      • Epoxy guiderods to ITMY (Afternoon)
      • Cure epoxy (overnight)
  • Sat 20 Feb
    • No Electricity - No work
  • Sun 21 Feb
  • Mon 22 Feb
    • ITMX magnet gluing

      • Remove ITMX from guiderod fixture, place in magnet fixture
      • Epoxy magnets ITMX (Afternoon)
      • Cure epoxy (overnight)
    • EQ stop preparation

      • Talk to Zach - help him get started on this
      • Plan for viton cutting (something to help measure / keep the razor straight while cutting)
      • Cut the Viton
      • Assemble EQ stops (stick the viton in the screws)
  • Tues 23 Feb
    • EQ stop preparation

      • Zach finish making EQ stops (at least enough for the ITMs...can finish the rest later in the week)
    • Hanging preparation

      • Balance Optical Table (Morning)
      • Make HeNe OpLev (Morning)

      • Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
    • ITMY magnet gluing

      • Glue magnets to ITMY (Afternoon)
      • Cure epoxy (overnight)
  • Tue 2 Mar (actual date)

    • ITMX hanging

      • Hang and balance ITMX. (All Day)
      • Epoxy wire standoffs in place after balancing
      • Cure epoxy (overnight)
  • Tue 11 Mar (actual date)

    • ITMY hanging

      • Hang and balance ITMY. (All Day)
      • Epoxy wire standoffs in place after balancing
      • Cure epoxy (overnight)
  • Mon 22 Mar (actual date)

    • ITMX/ITMY baking - done

      • Remove both ITMs from their suspensions (Morning) 2 person job
      • Vacuum bake to clean the optics - 48 hours
      • Leave the 2 ITMs alone in the bake oven
      • Get RGA scan to confirm they're sparkly clean
  • Mon 5 Apr (actual date)

    • Final Prep for Installation

      • Reinstall optics in suspensions (Definitely a 2 person job)
      • Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs)