| Describe Past Plans here. | === Week of 2/16-2/19 === * '''2/16-19 Pre-vent works''' * Tuning of the MC servo ~ low power MC test * End X/Y transmon optics relocations ~ making spaces for green * ITM pointing preparations ~ green/red pointers at the both ends * '''2/17 40m meeting''' * '''2/18 Power shutdown preparation''' * '''2/19 No work / only papers and pens''' * '''2/20 Power shutdown''' === Week of 2/22-2/26 === * '''2/22 Power shutdown recovery''' * System recovery * Check MC SOS status * Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident) * Pre-vent check list * PZT HV / Oplevs / etc * '''2/23 Reserved for trouble shooting''' * '''2/23 or 24 Vent''' * '''2/24 40m meeting ''' * '''2/25 Tank opening''' * OMC/IMC access connector * ITMX/Y heavy door * '''2/25 Input MC beam adjustment''' * beam centering to MC mirrors |
Week of 2/16-2/19
2/16-19 Pre-vent works
- Tuning of the MC servo ~ low power MC test
- End X/Y transmon optics relocations ~ making spaces for green
- ITM pointing preparations ~ green/red pointers at the both ends
2/17 40m meeting
2/18 Power shutdown preparation
2/19 No work / only papers and pens
2/20 Power shutdown
Week of 2/22-2/26
2/22 Power shutdown recovery
- System recovery
- Check MC SOS status
Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
- Pre-vent check list
- PZT HV / Oplevs / etc
2/23 Reserved for trouble shooting
2/23 or 24 Vent
2/24 40m meeting
2/25 Tank opening
- OMC/IMC access connector
- ITMX/Y heavy door
2/25 Input MC beam adjustment
- beam centering to MC mirrors