Cleaning of the suspended test mass
Motivation
Whether contamination or nor.
== Measurements before the vent ==
== Overview of the plan ==
We plan for the vent from 7th Dec to 11th Dec in 2009.
== Detailed plan ==
- wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV
Monday - Vent
Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs)
- Wiping Practice
ETMX ETMY ITMY ITMX (hardest)
- IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers
Thursday - Evacuation
Friday