       * look that we have good RGA scan
  

Cleaning of the suspended test mass (Dec 2009)

Motivation

Whether contamination or not

Measurements before the vent

- Visibility measurement

- Finesse measurement

Overview of the plan

  • We plan for the vent from 7th Dec to 11th Dec in 2009.

  • Preparation

    • wiping preparation
    • wiping practice
    • aux beam as a reference....align to overlap in vacuum
    • Input PZT (strain gauge) /HV off/OMC PZT HV
      • update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges)
      • recenter: IP-ANG-POS, oplevs..... at full lock
    • test drive crane drives
    • clean clean-tools again
    • keep eyes on particle counter: abort over 10,000
    • cut some viton tips for spare earthquake stop screws
    • look that we have good RGA scan
  • Monday:

    • Vent / Open ETMX if possible
    • Take pictures before touching
    • Record positions of the mirrors (OSEMs/OPLEVs)
  • Tuesday:

    • ETMX wipe
    • ETMY wipe
  • ~ Wednessday:

    • IPANG beam
    • ITMX position (pushing screws)
    • ITMX BB leveling
    • measure the distance of the breadboards
    • check of the optics in the chambers
    • ITMY wipe
    • ITMX wipe
  • Thursday: - Evacuation

  • Friday:

Detailed plan

  • Friday, 4 Dec:

    • Practice cutting viton, so we can get the correct sizes if we need to replace stops. (Jenne)
    • Recenter all of our pointing PDs (oplevs and IP_POS, IP_ANG).
    • Update snapshots of all MEDM screens that have alignment information.
    • Move extraneous equipment around chamber doors: Make sure we have clear access (esp. seismometers need moving)
  • Monday:

    • Before venting, check that all the recentering done on Friday is still good. If not, redo.
    • Vent
    • During vent, practice drag wiping a spare random optic (maybe a 2" CVI optic?)
    • Open ETMX
    • Take photos of ETMX before touching
    • Close up ETMX with light doors for the night
  • Tuesday:

  • Wednesday:

  • Thursday:

  • Friday: