Differences between revisions 4 and 6 (spanning 2 versions)
Revision 4 as of 2009-12-03 00:50:00
Size: 709
Editor: KojiArai
Comment:
Revision 6 as of 2009-12-03 02:30:58
Size: 848
Editor: KojiArai
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
=== - Visibility measurement ===
=== - Finesse measurement ===
Line 7: Line 9:
We plan for the vent from 7th Dec to 11th Dec in 2009.  * '''We plan for the vent from 7th Dec to 11th Dec in 2009.  '''
Line 9: Line 11:
- wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV  * '''Preparation '''
  *
wiping preparation
 * wiping practice
* aux beam as a reference
 * Input PZT (strain gauge) /HV off/OMC PZT HV
Line 11: Line 17:
Monday - Vent  * '''Monday:'''
  * Vent / Open ETMX if possible
  * Take pictures before touching
  * Record positions of the mirrors (OSEMs/OPLEVs)
Line 13: Line 22:
Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs)  * '''~ Wednessday:'''
 - IPANG beam
 - ITMX position (pushing screws)
 - ITMX BB leveling
 - measure the distance of the breadboards
 - check of the optics in the chambers
Line 15: Line 29:
- Wiping Practice  * '''Thursday:''' - Evacuation
Line 17: Line 31:
ETMX ETMY ITMY ITMX (hardest)

- IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers

Thursday - Evacuation

Friday
 * '''Friday: '''

Cleaning of the suspended test mass (Dec 2009)

Motivation

Whether contamination or not

Measurements before the vent

- Visibility measurement

- Finesse measurement

Overview of the plan

  • We plan for the vent from 7th Dec to 11th Dec in 2009.

  • Preparation

    • wiping preparation
    • wiping practice
    • aux beam as a reference
    • Input PZT (strain gauge) /HV off/OMC PZT HV
  • Monday:

    • Vent / Open ETMX if possible
    • Take pictures before touching
    • Record positions of the mirrors (OSEMs/OPLEVs)
  • ~ Wednessday: - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers

  • Thursday: - Evacuation

  • Friday:

Detailed plan

Optics_Cleaning (last edited 2012-01-03 23:02:40 by localhost)