Line 6: Line 6:
=== - Visibility measurement ===
=== - Finesse measurement ===
Line 7: Line 9:
We plan for the vent from 7th Dec to 11th Dec in 2009.  * We plan for the vent from 7th Dec to 11th Dec in 2009. 
Line 9: Line 11:
- wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV  * Preparation
  *
wiping preparation
 * wiping practice
* aux beam as a reference
 * Input PZT (strain gauge) /HV off/OMC PZT HV 
Line 11: Line 17:
Monday - Vent  * '''Monday:'''
Line 13: Line 19:
Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs)   * Vent / Open ETMX if possible
 * Take pictures before touching
 * Record positions of the mirrors (OSEMs/OPLEVs)
Line 15: Line 23:
- Wiping Practice  * '''~ Wednessday:'''
Line 17: Line 25:
ETMX ETMY ITMY ITMX (hardest)  - IPANG beam
Line 19: Line 27:
- IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers
Line 21: Line 28:
Thursday - Evacuation  - ITMX position (pushing screws)
Line 23: Line 30:
Friday
 - ITMX BB leveling


 - measure the distance of the breadboards


 - check of the optics in the chambers

 * '''Thursday:''' - Evacuation

 * '''Friday: '''

Cleaning of the suspended test mass (Dec 2009)

Motivation

Whether contamination or not

Measurements before the vent

- Visibility measurement

- Finesse measurement

Overview of the plan

  • We plan for the vent from 7th Dec to 11th Dec in 2009.
  • Preparation
    • wiping preparation
    • wiping practice
    • aux beam as a reference
    • Input PZT (strain gauge) /HV off/OMC PZT HV
  • Monday:

    • Vent / Open ETMX if possible
    • Take pictures before touching
    • Record positions of the mirrors (OSEMs/OPLEVs)
  • ~ Wednessday: - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers

  • Thursday: - Evacuation

  • Friday:

Detailed plan