| Whether contamination or not | The round trip loss in the 40m cavity is estimated to be around 160ppm. We are going to confirm wether this comes from the hydrocarbon contamination and wiping of the mirror by acetone and isopropy may result in improvement of the optical loss, or not. |
| Line 5: | Line 5: |
| == Measurements before the vent == | In addition we cna evaluate the use of those solvents. If we observe the degradation of the loss or the finesse, we will forbid them. == Measurements before the cleaning == === - Visibility measurement === Most recent arm visibility measurement has been done on Oct 07, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2070 corresponding elog entry] {{{ Measured arm reflectivity R_cav: X arm: 0.875 +/- 0.005 Y arm: 0.869 +/- 0.006 }}} === - Cavity pole measurement === Most recent arm visibility measurement has been done on Nov 10, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2226 corresponding elog entry] {{{ Measured arm cavity pole frequency f_pole [Hz]: X arm: 1720 +/- 70 Y arm: 1650 +/- 70 }}} === - Estimated finesse === == Measurements after the cleaning == === - Visibility measurement === === - Cavity pole measurement === === - Estimated finesse === ------- |
| Line 7: | Line 33: |
| We plan for the vent from 7th Dec to 11th Dec in 2009. | * '''We plan for the vent from 7th Dec to 11th Dec in 2009. ''' |
| Line 9: | Line 35: |
| - wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV | * '''Preparation ''' * Wiping Preparation * Vent Preparation |
| Line 11: | Line 39: |
| Monday - Vent | * '''Monday:''' * Pre-vent check 8:00~ * Vent from 9:30~ * Stop venting ~14:00 * Check OSEM/Oplev values * Wipe ETMX 14:00~ * Open ETMX 14:00~15:00 * Mirror wiping 15:00~16:00 * Check alignment / Close up 16:00~17:00 |
| Line 13: | Line 49: |
| Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs) | * '''Tuesday:''' * (ETMX wipe) * ETMY wipe * ITMY wipe * Check of the optics in the chambers (ITMY) |
| Line 15: | Line 55: |
| - Wiping Practice | * '''~ Wednessday:''' * ITMX wipe * Record ITMX position (pushing screws) * ITMX BB leveling * measure the distance of the breadboards * 40m meeting * Check of the optics in the chambers (ITMX/BS) |
| Line 17: | Line 63: |
| ETMX ETMY ITMY ITMX (hardest) | * '''Thursday:''' * Evacuation |
| Line 19: | Line 66: |
| - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers Thursday - Evacuation Friday |
* '''Friday:''' * Reserve |
| Line 26: | Line 70: |
| * '''~Friday, 4 Dec: ''' * Wiping preparation * Chemicals: small bottles (like 250ml) / 3 bottles each (no matter how the size is), '''Acetone''' Spectral Grade, dehydrated (if possible), '''Isopropyl alcohol''' Spectral Grade, dehydrated (if possible) * glass sylinges with metal needles, 50ul, at least three sets * mirror wiping paper, usual lens paper from Kodak or whatever * tools (well cleaned) * clamps to mark the position of ITMX: 3pcs * halogen light or whatever: light during the work * '''Vent Preparation ''' * Clean clean-tools again * Alignment * Recenter: IPANG/POS, oplevs with the mirrors fully aligned '''[DONE]''' * Align the aux beam as a reference '''[DONE]''' * Update snapshots of all MEDM screens for OSEMs/OPLEVs/QPDs/PZT&strain gauges '''[DONE]''' * Move extraneous equipment around chamber doors: Make sure we have clear access (esp. seismometers need moving) '''[DONE]''' * '''Monday: ''' * Before venting, check that all the recentering done on Friday is still good. If not, redo. * Turn off all HV in vacuum (Input/Output PZT) * '''Vent''' * During the vent - Door opening preparation * Test drive crane drives * Move and store abs. length setup to a safe place * Practice drag wiping a spare random optic (with an arbitrary 2" CVI optic) * Practice cutting viton, so we can get the correct sizes if we need to replace stops. (Jenne) * Cut some viton tips for spare earthquake stop screws * Environment * Keep eyes on particle counter: abort over 10,000 * Look that we have good RGA scan * Open ETMX * Take photos of ETMX before touching * '''ETMX wipe''' * Close up ETMX with light doors for the night * '''Tuesday: ''' * '''Wednesday: ''' * '''Thursday: ''' * '''Friday: ''' |
Cleaning of the suspended test mass (Dec 2009)
Motivation
The round trip loss in the 40m cavity is estimated to be around 160ppm. We are going to confirm wether this comes from the hydrocarbon contamination and wiping of the mirror by acetone and isopropy may result in improvement of the optical loss, or not.
In addition we cna evaluate the use of those solvents. If we observe the degradation of the loss or the finesse, we will forbid them.
Measurements before the cleaning
- Visibility measurement
Most recent arm visibility measurement has been done on Oct 07, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2070 corresponding elog entry]
Measured arm reflectivity R_cav: X arm: 0.875 +/- 0.005 Y arm: 0.869 +/- 0.006
- Cavity pole measurement
Most recent arm visibility measurement has been done on Nov 10, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2226 corresponding elog entry]
Measured arm cavity pole frequency f_pole [Hz]: X arm: 1720 +/- 70 Y arm: 1650 +/- 70
- Estimated finesse
Measurements after the cleaning
- Visibility measurement
- Cavity pole measurement
- Estimated finesse
Overview of the plan
We plan for the vent from 7th Dec to 11th Dec in 2009.
Preparation
- Wiping Preparation
- Vent Preparation
Monday:
- Pre-vent check 8:00~
- Vent from 9:30~
- Stop venting ~14:00
- Check OSEM/Oplev values
- Wipe ETMX 14:00~
- Open ETMX 14:00~15:00
- Mirror wiping 15:00~16:00
- Check alignment / Close up 16:00~17:00
Tuesday:
- (ETMX wipe)
- ETMY wipe
- ITMY wipe
- Check of the optics in the chambers (ITMY)
~ Wednessday:
- ITMX wipe
- Record ITMX position (pushing screws)
- ITMX BB leveling
- measure the distance of the breadboards
- 40m meeting
- Check of the optics in the chambers (ITMX/BS)
- ITMX wipe
Thursday:
- Evacuation
Friday:
- Reserve
Detailed plan
~Friday, 4 Dec:
- Wiping preparation
Chemicals: small bottles (like 250ml) / 3 bottles each (no matter how the size is), Acetone Spectral Grade, dehydrated (if possible), Isopropyl alcohol Spectral Grade, dehydrated (if possible)
- glass sylinges with metal needles, 50ul, at least three sets
- mirror wiping paper, usual lens paper from Kodak or whatever
- tools (well cleaned)
- clamps to mark the position of ITMX: 3pcs
- halogen light or whatever: light during the work
- Wiping preparation
Vent Preparation
- Clean clean-tools again
- Alignment
Recenter: IPANG/POS, oplevs with the mirrors fully aligned [DONE]
Align the aux beam as a reference [DONE]
Update snapshots of all MEDM screens for OSEMs/OPLEVs/QPDs/PZT&strain gauges [DONE]
Move extraneous equipment around chamber doors: Make sure we have clear access (esp. seismometers need moving) [DONE]
Monday:
- Before venting, check that all the recentering done on Friday is still good. If not, redo.
- Turn off all HV in vacuum (Input/Output PZT)
Vent
- During the vent - Door opening preparation
- Test drive crane drives
- Move and store abs. length setup to a safe place
- Practice drag wiping a spare random optic (with an arbitrary 2" CVI optic)
- Practice cutting viton, so we can get the correct sizes if we need to replace stops. (Jenne)
- Cut some viton tips for spare earthquake stop screws
- Environment
- Keep eyes on particle counter: abort over 10,000
- Look that we have good RGA scan
- Open ETMX
- Take photos of ETMX before touching
ETMX wipe
- Close up ETMX with light doors for the night
Tuesday:
Wednesday:
Thursday:
Friday: