Size: 706
Comment:
|
Size: 1202
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 1: | Line 1: |
| = Cleaning of the suspended test mass = |
= Cleaning of the suspended test mass (Dec 2009) = |
| Line 4: | Line 3: |
| Line 8: | Line 6: |
| === - Visibility measurement === === - Finesse measurement === == Overview of the plan == * '''We plan for the vent from 7th Dec to 11th Dec in 2009. ''' |
|
| Line 9: | Line 11: |
| == Overview of the plan == | * '''Preparation ''' * wiping preparation * wiping practice * aux beam as a reference....align to overlap in vacuum * Input PZT (strain gauge) /HV off/OMC PZT HV * update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges) * recenter: IP-ANG-POS, oplevs..... at full lock * test drive crane drives * clean clean-tools again * keep eyes on particle counter: abort over 10,000 * cut some viton tips for spare earthquake stop screws * '''Monday:''' * Vent / Open ETMX if possible * Take pictures before touching * Record positions of the mirrors (OSEMs/OPLEVs) |
| Line 11: | Line 28: |
| We plan for the vent from 7th Dec to 11th Dec in 2009. | * '''~ Wednessday:''' - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers |
| Line 13: | Line 35: |
| - wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV | * '''Thursday:''' - Evacuation |
| Line 15: | Line 37: |
| Monday - Vent Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs) - Wiping Practice ETMX ETMY ITMY ITMX (hardest) - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers Thursday - Evacuation Friday |
* '''Friday: ''' |
Cleaning of the suspended test mass (Dec 2009)
Motivation
Whether contamination or not
Measurements before the vent
- Visibility measurement
- Finesse measurement
Overview of the plan
We plan for the vent from 7th Dec to 11th Dec in 2009.
Preparation
- wiping preparation
- wiping practice
- aux beam as a reference....align to overlap in vacuum
- Input PZT (strain gauge) /HV off/OMC PZT HV
- update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges)
- recenter: IP-ANG-POS, oplevs..... at full lock
- test drive crane drives
- clean clean-tools again
- keep eyes on particle counter: abort over 10,000
- cut some viton tips for spare earthquake stop screws
Monday:
- Vent / Open ETMX if possible
- Take pictures before touching
- Record positions of the mirrors (OSEMs/OPLEVs)
~ Wednessday: - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers
Thursday: - Evacuation
Friday: