= Cleaning of the suspended test mass =
= Cleaning of the suspended test mass (Dec 2009) =
Line 4: Line 3:
Line 8: Line 6:
=== - Visibility measurement ===
=== - Finesse measurement ===
== Overview of the plan ==
 * We plan for the vent from 7th Dec to 11th Dec in 2009.
Line 9: Line 11:
== Overview of the plan ==  * Preparation
  * wiping preparation
  * wiping practice
  * aux beam as a reference
  * Input PZT (strain gauge) /HV off/OMC PZT HV
Line 11: Line 17:
We plan for the vent from 7th Dec to 11th Dec in 2009.  * '''Monday:'''
Line 13: Line 19:
- wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV   * Vent / Open ETMX if possible
  * Take pictures before touching
  * Record positions of the mirrors (OSEMs/OPLEVs)
Line 15: Line 23:
Monday - Vent  * '''~ Wednessday:'''
Line 17: Line 25:
Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs)  - IPANG beam
Line 19: Line 27:
- Wiping Practice
Line 21: Line 28:
ETMX ETMY ITMY ITMX (hardest)  - ITMX position (pushing screws)
Line 23: Line 30:
- IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers
Line 25: Line 31:
Thursday - Evacuation  - ITMX BB leveling
Line 27: Line 33:
Friday
 - measure the distance of the breadboards


 - check of the optics in the chambers

 * '''Thursday:''' - Evacuation

 * '''Friday: '''

Cleaning of the suspended test mass (Dec 2009)

Motivation

Whether contamination or not

Measurements before the vent

- Visibility measurement

- Finesse measurement

Overview of the plan

  • We plan for the vent from 7th Dec to 11th Dec in 2009.
  • Preparation
    • wiping preparation
    • wiping practice
    • aux beam as a reference
    • Input PZT (strain gauge) /HV off/OMC PZT HV
  • Monday:

    • Vent / Open ETMX if possible
    • Take pictures before touching
    • Record positions of the mirrors (OSEMs/OPLEVs)
  • ~ Wednessday: - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers

  • Thursday: - Evacuation

  • Friday:

Detailed plan