Cleaning of the suspended test mass (Dec 2009)
Motivation
Whether contamination or not
Measurements before the vent
Overview of the plan
We plan for the vent from 7th Dec to 11th Dec in 2009.
- wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV
Monday - Vent
Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs)
- Wiping Practice
ETMX ETMY ITMY ITMX (hardest)
- IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers
Thursday - Evacuation
Friday