= Cleaning of the suspended test mass = = Cleaning of the suspended test mass (Dec 2009) =
Line 6: Line 6:
=== - Visibility measurement ===
=== - Finesse measurement ===
Line 7: Line 9:
We plan for the vent from 7th Dec to 11th Dec in 2009.  * '''We plan for the vent from 7th Dec to 11th Dec in 2009. '''

 * '''Preparation '''
  * wiping preparation
  * wiping practice
  * aux beam as a reference....align to overlap in vacuum
  * Input PZT (strain gauge) /HV off/OMC PZT HV
    * update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges)
    * recenter: IP-ANG-POS, oplevs..... at full lock
    * test drive crane drives
    * clean clean-tools again
    * keep eyes on particle counter: abort over 10,000
    * cut some viton tips for spare earthquake stop screws
    
 * '''Monday:'''
  * Vent / Open ETMX if possible
  * Take pictures before touching
  * Record positions of the mirrors (OSEMs/OPLEVs)

 * '''~ Wednessday:'''
 - IPANG beam
 - ITMX position (pushing screws)
 - ITMX BB leveling
 - measure the distance of the breadboards
 - check of the optics in the chambers

 * '''Thursday:''' - Evacuation

 * '''Friday: '''
Line 10: Line 40:
- wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV

Monday - Vent

Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs)

- Wiping Practice

ETMX ETMY ITMY ITMX (hardest)

- IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers

Thursday - Evacuation

Friday

Cleaning of the suspended test mass (Dec 2009)

Motivation

Whether contamination or not

Measurements before the vent

- Visibility measurement

- Finesse measurement

Overview of the plan

  • We plan for the vent from 7th Dec to 11th Dec in 2009.

  • Preparation

    • wiping preparation
    • wiping practice
    • aux beam as a reference....align to overlap in vacuum
    • Input PZT (strain gauge) /HV off/OMC PZT HV
      • update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges)
      • recenter: IP-ANG-POS, oplevs..... at full lock
      • test drive crane drives
      • clean clean-tools again
      • keep eyes on particle counter: abort over 10,000
      • cut some viton tips for spare earthquake stop screws
  • Monday:

    • Vent / Open ETMX if possible
    • Take pictures before touching
    • Record positions of the mirrors (OSEMs/OPLEVs)
  • ~ Wednessday: - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers

  • Thursday: - Evacuation

  • Friday:

Detailed plan