Size: 696
Comment:
|
Size: 4540
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 1: | Line 1: |
| = Cleaning of the suspended test mass = | = Cleaning of the suspended test mass (Dec 2009) = |
| Line 3: | Line 3: |
| Whether contamination or not | The round trip loss in the 40m cavity is estimated to be around 160ppm. We are going to confirm wether this comes from the hydrocarbon contamination and wiping of the mirror by acetone and isopropy may result in improvement of the optical loss, or not. In addition we cna evaluate the use of those solvents. If we observe the degradation of the loss or the finesse, we will forbid them. |
| Line 6: | Line 8: |
| === - Visibility measurement === Most recent arm visibility measurement has been done on Oct 07, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2070 corresponding elog entry] {{{ Measured arm reflectivity R_cav: X arm: 0.875 +/- 0.005 Y arm: 0.869 +/- 0.006 }}} === - Cavity pole measurement === Most recent arm visibility measurement has been done on Nov 10, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2226 corresponding elog entry] {{{ Measured arm cavity pole frequency f_pole [Hz]: X arm: 1720 +/- 70 Y arm: 1650 +/- 70 }}} |
|
| Line 7: | Line 27: |
| We plan for the vent from 7th Dec to 11th Dec in 2009. | * '''We plan for the vent from 7th Dec to 11th Dec in 2009. ''' * '''Preparation ''' * wiping preparation * wiping practice * aux beam as a reference....align to overlap in vacuum * Input PZT (strain gauge) /HV off/OMC PZT HV * update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges) * recenter: IP-ANG-POS, oplevs..... at full lock * test drive crane drives * clean clean-tools again * keep eyes on particle counter: abort over 10,000 * cut some viton tips for spare earthquake stop screws * look that we have good RGA scan * '''Monday:''' * Vent / Open ETMX if possible * Take pictures before touching * Record positions of the mirrors (OSEMs/OPLEVs) * '''Tuesday:''' * ETMX wipe * ETMY wipe * '''~ Wednessday:''' * IPANG beam * ITMX position (pushing screws) * ITMX BB leveling * measure the distance of the breadboards * check of the optics in the chambers * ITMY wipe * ITMX wipe * '''Thursday:''' - Evacuation * '''Friday: ''' |
| Line 10: | Line 65: |
| - wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV | * '''~Friday, 4 Dec: ''' * Wiping preparation * Chemicals: small bottles (like 250ml) / 3 bottles each (no matter how the size is), '''Acetone''' Spectral Grade, dehydrated (if possible), '''Isopropyl alcohol''' Spectral Grade, dehydrated (if possible) * glass sylinges with metal needles, 50ul, at least three sets * mirror wiping paper, usual lens paper from Kodak or whatever * tools (well cleaned) * clamps to mark the position of ITMX: 3pcs * halogen light or whatever: light during the work |
| Line 12: | Line 74: |
| Monday - Vent | * '''Friday, 4 Dec: ''' * Practice cutting viton, so we can get the correct sizes if we need to replace stops. (Jenne) * Recenter all of our pointing PDs (oplevs and IP_POS, IP_ANG). (DONE 10pm Friday) * Update snapshots of all MEDM screens that have alignment information. (DONE 10pm Friday) * Move extraneous equipment around chamber doors: Make sure we have clear access (esp. seismometers need moving) (DONE 5pm Friday) * '''o Go to only ITMX mode:''' Save the alignment of the mirrors. Activate X-arm mode. Misalign ITMY and ETMX. '''o Inject the aux beam:''' Open the shutter of the aux NPRO. Turn the injection flipper on. '''o Look at the faraday output:''' There are several spots but only one was the right one. Confirm the alignment to the thorlabs PD. Connect the oscilloscope to the PD out with a 50Ohm termination. Thanks to the Alberto's adjustment, the beat was already there at around 10MHz. After the PD adjustment, the DC was about 600mV, the beat amplitude was about 50mVpp. '''o Adjust the aux beam alignment: ''' Adjust the alignment of the aux beam by '''the steering mirrors before the farady isolator.''' These only change the alignment of the aux beam independently from the IFO beam. After the alignment, the beat amplitude of 100mVpp was obtained. '''o Closing '''Close the shutter of the NPRO. Turn off the flipper mirror. Restore the full alignment of the IFO. |
| Line 14: | Line 93: |
| Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs) | * '''Monday: ''' * Before venting, check that all the recentering done on Friday is still good. If not, redo. * Vent * During vent, practice drag wiping a spare random optic (maybe a 2" CVI optic?) * Open ETMX * Take photos of ETMX before touching * Close up ETMX with light doors for the night |
| Line 16: | Line 101: |
| - Wiping Practice | * '''Tuesday: ''' |
| Line 18: | Line 103: |
| ETMX ETMY ITMY ITMX (hardest) | * '''Wednesday: ''' |
| Line 20: | Line 105: |
| - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers | * '''Thursday: ''' |
| Line 22: | Line 107: |
| Thursday - Evacuation Friday |
* '''Friday: ''' |
Cleaning of the suspended test mass (Dec 2009)
Motivation
The round trip loss in the 40m cavity is estimated to be around 160ppm. We are going to confirm wether this comes from the hydrocarbon contamination and wiping of the mirror by acetone and isopropy may result in improvement of the optical loss, or not.
In addition we cna evaluate the use of those solvents. If we observe the degradation of the loss or the finesse, we will forbid them.
Measurements before the vent
- Visibility measurement
Most recent arm visibility measurement has been done on Oct 07, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2070 corresponding elog entry]
Measured arm reflectivity R_cav: X arm: 0.875 +/- 0.005 Y arm: 0.869 +/- 0.006
- Cavity pole measurement
Most recent arm visibility measurement has been done on Nov 10, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2226 corresponding elog entry]
Measured arm cavity pole frequency f_pole [Hz]: X arm: 1720 +/- 70 Y arm: 1650 +/- 70
Overview of the plan
We plan for the vent from 7th Dec to 11th Dec in 2009.
Preparation
- wiping preparation
- wiping practice
- aux beam as a reference....align to overlap in vacuum
- Input PZT (strain gauge) /HV off/OMC PZT HV
- update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges)
- recenter: IP-ANG-POS, oplevs..... at full lock
- test drive crane drives
- clean clean-tools again
- keep eyes on particle counter: abort over 10,000
- cut some viton tips for spare earthquake stop screws
- look that we have good RGA scan
Monday:
- Vent / Open ETMX if possible
- Take pictures before touching
- Record positions of the mirrors (OSEMs/OPLEVs)
Tuesday:
- ETMX wipe
- ETMY wipe
~ Wednessday:
- IPANG beam
- ITMX position (pushing screws)
- ITMX BB leveling
- measure the distance of the breadboards
- check of the optics in the chambers
- ITMY wipe
- ITMX wipe
Thursday: - Evacuation
Friday:
Detailed plan
~Friday, 4 Dec:
- Wiping preparation
Chemicals: small bottles (like 250ml) / 3 bottles each (no matter how the size is), Acetone Spectral Grade, dehydrated (if possible), Isopropyl alcohol Spectral Grade, dehydrated (if possible)
- glass sylinges with metal needles, 50ul, at least three sets
- mirror wiping paper, usual lens paper from Kodak or whatever
- tools (well cleaned)
- clamps to mark the position of ITMX: 3pcs
- halogen light or whatever: light during the work
- Wiping preparation
Friday, 4 Dec:
- Practice cutting viton, so we can get the correct sizes if we need to replace stops. (Jenne)
- Recenter all of our pointing PDs (oplevs and IP_POS, IP_ANG). (DONE 10pm Friday)
- Update snapshots of all MEDM screens that have alignment information. (DONE 10pm Friday)
- Move extraneous equipment around chamber doors: Make sure we have clear access (esp. seismometers need moving) (DONE 5pm Friday)
o Go to only ITMX mode:
o Inject the aux beam:
o Look at the faraday output:
o Adjust the aux beam alignment:
Adjust the alignment of the aux beam by the steering mirrors before the farady isolator. These only change the alignment of the aux beam independently from the IFO beam. After the alignment, the beat amplitude of 100mVpp was obtained.
o Closing Close the shutter of the NPRO. Turn off the flipper mirror. Restore the full alignment of the IFO.
Monday:
- Before venting, check that all the recentering done on Friday is still good. If not, redo.
- Vent
- During vent, practice drag wiping a spare random optic (maybe a 2" CVI optic?)
- Open ETMX
- Take photos of ETMX before touching
- Close up ETMX with light doors for the night
Tuesday:
Wednesday:
Thursday:
Friday: