= Cleaning of the suspended test mass = = Cleaning of the suspended test mass (Dec 2009) =
== Motivation ==
Whether contamination or not
Line 3: Line 5:
== Motivation == == Measurements before the vent ==
=== - Visibility measurement ===
=== - Finesse measurement ===
== Overview of the plan ==
 * '''We plan for the vent from 7th Dec to 11th Dec in 2009. '''
Line 5: Line 11:
Whether contamination or nor.  * '''Preparation '''
  * wiping preparation
  * wiping practice
  * aux beam as a reference....align to overlap in vacuum
  * Input PZT (strain gauge) /HV off/OMC PZT HV
    * update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges)
    * recenter: IP-ANG-POS, oplevs..... at full lock
    * test drive crane drives
    * clean clean-tools again
    * keep eyes on particle counter: abort over 10,000
    * cut some viton tips for spare earthquake stop screws
    
 * '''Monday:'''
  * Vent / Open ETMX if possible
  * Take pictures before touching
  * Record positions of the mirrors (OSEMs/OPLEVs)
Line 7: Line 28:
== Measurements before the vent ==  * '''~ Wednessday:'''
 - IPANG beam
 - ITMX position (pushing screws)
 - ITMX BB leveling
 - measure the distance of the breadboards
 - check of the optics in the chambers
Line 9: Line 35:
== Overview of the plan ==  * '''Thursday:''' - Evacuation
Line 11: Line 37:
We plan for the vent from 7th Dec to 11th Dec in 2009.  * '''Friday: '''
Line 13: Line 39:
== Detailed plan ==

- wiping preparation
- wiping practice
- aux beam as a reference
- Input PZT (strain gauge) /HV off/OMC PZT HV

Monday
- Vent

Tuesday-Wednessday
- Take pictures before touching
- position of the mirrors (OSEMs/OPLEVs)

- Wiping
Practice

ETMX
ETMY
ITMY
ITMX (hardest)

- IPANG beam
- ITMX position (pushing screws)
- ITMX BB leveling
- measure the distance of the breadboards
- check of the optics in the chambers

Thursday
- Evacuation

Friday
== Detailed plan ==

Cleaning of the suspended test mass (Dec 2009)

Motivation

Whether contamination or not

Measurements before the vent

- Visibility measurement

- Finesse measurement

Overview of the plan

  • We plan for the vent from 7th Dec to 11th Dec in 2009.

  • Preparation

    • wiping preparation
    • wiping practice
    • aux beam as a reference....align to overlap in vacuum
    • Input PZT (strain gauge) /HV off/OMC PZT HV
      • update snap shots: sus, strain gauges,IOO, OMC....etc (OMC has no strain gauges)
      • recenter: IP-ANG-POS, oplevs..... at full lock
      • test drive crane drives
      • clean clean-tools again
      • keep eyes on particle counter: abort over 10,000
      • cut some viton tips for spare earthquake stop screws
  • Monday:

    • Vent / Open ETMX if possible
    • Take pictures before touching
    • Record positions of the mirrors (OSEMs/OPLEVs)
  • ~ Wednessday: - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers

  • Thursday: - Evacuation

  • Friday:

Detailed plan