Size: 725
Comment:
|
Size: 861
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 1: | Line 1: |
| = Cleaning of the suspended test mass = | = Cleaning of the suspended test mass (Dec 2009) = == Motivation == Whether contamination or not |
| Line 3: | Line 5: |
| == Motivation == | == Measurements before the vent == === - Visibility measurement === === - Finesse measurement === == Overview of the plan == * We plan for the vent from 7th Dec to 11th Dec in 2009. |
| Line 5: | Line 11: |
| Whether contamination or nor. | * Preparation * wiping preparation * wiping practice * aux beam as a reference * Input PZT (strain gauge) /HV off/OMC PZT HV |
| Line 7: | Line 17: |
| == Measurements before the vent == | * '''Monday:''' |
| Line 9: | Line 19: |
| == Overview of the plan == | * Vent / Open ETMX if possible * Take pictures before touching * Record positions of the mirrors (OSEMs/OPLEVs) |
| Line 11: | Line 23: |
| We plan for the vent from 7th Dec to 11th Dec in 2009. | * '''~ Wednessday:''' |
| Line 13: | Line 25: |
| == Detailed plan == | - IPANG beam |
| Line 15: | Line 27: |
| - wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV |
|
| Line 20: | Line 28: |
| Monday - Vent |
- ITMX position (pushing screws) |
| Line 23: | Line 30: |
| Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs) |
|
| Line 27: | Line 31: |
| - Wiping Practice |
- ITMX BB leveling |
| Line 30: | Line 33: |
| ETMX ETMY ITMY ITMX (hardest) |
|
| Line 35: | Line 34: |
| - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers |
- measure the distance of the breadboards |
| Line 41: | Line 36: |
| Thursday - Evacuation |
|
| Line 44: | Line 37: |
| Friday | - check of the optics in the chambers * '''Thursday:''' - Evacuation * '''Friday: ''' == Detailed plan == |
Cleaning of the suspended test mass (Dec 2009)
Motivation
Whether contamination or not
Measurements before the vent
- Visibility measurement
- Finesse measurement
Overview of the plan
- We plan for the vent from 7th Dec to 11th Dec in 2009.
- Preparation
- wiping preparation
- wiping practice
- aux beam as a reference
- Input PZT (strain gauge) /HV off/OMC PZT HV
Monday:
- Vent / Open ETMX if possible
- Take pictures before touching
- Record positions of the mirrors (OSEMs/OPLEVs)
~ Wednessday: - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers
Thursday: - Evacuation
Friday: