Size: 725
Comment:
|
Size: 709
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 1: | Line 1: |
| = Cleaning of the suspended test mass = | = Cleaning of the suspended test mass (Dec 2009) = == Motivation == Whether contamination or not |
| Line 3: | Line 5: |
| == Motivation == Whether contamination or nor. == Measurements before the vent == == Overview of the plan == |
== Measurements before the vent == == Overview of the plan == |
| Line 13: | Line 9: |
| == Detailed plan == | - wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV |
| Line 15: | Line 11: |
| - wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV |
Monday - Vent |
| Line 20: | Line 13: |
| Monday - Vent |
Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs) |
| Line 23: | Line 15: |
| Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs) |
- Wiping Practice |
| Line 27: | Line 17: |
| - Wiping Practice |
ETMX ETMY ITMY ITMX (hardest) |
| Line 30: | Line 19: |
| ETMX ETMY ITMY ITMX (hardest) |
- IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers |
| Line 35: | Line 21: |
| - IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers Thursday - Evacuation |
Thursday - Evacuation |
| Line 45: | Line 24: |
== Detailed plan == |
Cleaning of the suspended test mass (Dec 2009)
Motivation
Whether contamination or not
Measurements before the vent
Overview of the plan
We plan for the vent from 7th Dec to 11th Dec in 2009.
- wiping preparation - wiping practice - aux beam as a reference - Input PZT (strain gauge) /HV off/OMC PZT HV
Monday - Vent
Tuesday-Wednessday - Take pictures before touching - position of the mirrors (OSEMs/OPLEVs)
- Wiping Practice
ETMX ETMY ITMY ITMX (hardest)
- IPANG beam - ITMX position (pushing screws) - ITMX BB leveling - measure the distance of the breadboards - check of the optics in the chambers
Thursday - Evacuation
Friday