Differences between revisions 1 and 16 (spanning 15 versions)
Revision 1 as of 2009-12-03 00:47:45
Size: 725
Editor: KojiArai
Comment:
Revision 16 as of 2009-12-07 05:55:53
Size: 3921
Editor: KojiArai
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
= Cleaning of the suspended test mass = = Cleaning of the suspended test mass (Dec 2009) =
== Motivation ==
The round trip loss in the 40m cavity is estimated to be around 160ppm. We are going to confirm wether this comes from the hydrocarbon contamination and wiping of the mirror by acetone and isopropy may result in improvement of the optical loss, or not.
Line 3: Line 5:
== Motivation == In addition we cna evaluate the use of those solvents. If we observe the degradation of the loss or the finesse, we will forbid them.
Line 5: Line 7:
Whether contamination or nor. == Measurements before the cleaning ==
=== - Visibility measurement ===
Most recent arm visibility measurement has been done on Oct 07, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2070 corresponding elog entry]
Line 7: Line 11:
== Measurements before the vent == {{{
Measured arm reflectivity R_cav:
X arm: 0.875 +/- 0.005
Y arm: 0.869 +/- 0.006
}}}
Line 9: Line 17:
== Overview of the plan == === - Cavity pole measurement ===
Most recent arm visibility measurement has been done on Nov 10, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2226 corresponding elog entry]
Line 11: Line 20:
We plan for the vent from 7th Dec to 11th Dec in 2009. {{{
Measured arm cavity pole frequency f_pole [Hz]:
X arm: 1720 +/- 70
Y arm: 1650 +/- 70
}}}
Line 13: Line 26:
== Detailed plan ==  === - Estimated finesse ===
Line 15: Line 28:
- wiping preparation
- wiping practice
- aux beam as a reference
- Input PZT (strain gauge) /HV off/OMC PZT HV
== Measurements after the cleaning ==
=== - Visibility measurement ===
Line 20: Line 31:
Monday
- Vent
=== - Cavity pole measurement ===
Line 23: Line 33:
Tuesday-Wednessday
- Take pictures before touching
- position of the mirrors (OSEMs/OPLEVs)
=== - Estimated finesse ===
Line 27: Line 35:
- Wiping
Practice
-------
Line 30: Line 37:
ETMX
ETMY
ITMY
ITMX (hardest)
== Overview of the plan ==
 * '''We plan for the vent from 7th Dec to 11th Dec in 2009. '''
Line 35: Line 40:
- IPANG beam
- ITMX position (pushing screws)
- ITMX BB leveling
- measure the distance of the breadboards
- check of the optics in the chambers
 * '''Preparation '''
  * '''Wiping Preparation'''
  * '''Vent Preparation'''
Line 41: Line 44:
Thursday
- Evacuation
 * '''Monday:'''
  * Prevent check 8:00~
  * Vent from 9:30~
  * Stop venting ~14:00
  * Wipe ETMX 14:00~
   * Open ETMX 14:00~15:00
   * Mirror wiping 15:00~16:00
   * Check alignment / Close up 16:00~17:00
Line 44: Line 53:
Friday  * '''Tuesday:'''
  * (ETMX wipe)
  * ETMY wipe
  * ITMY wipe

 * '''~ Wednessday:'''
  * ITMX position (pushing screws)
  * ITMX BB leveling
  * measure the distance of the breadboards
  * check of the optics in the chambers

 * '''Thursday:'''
  * Evacuation

 * '''Friday:'''

== Detailed plan ==
 * '''~Friday, 4 Dec: '''
  * Wiping preparation
 * '''Wiping Preparation '''
  * Wiping preparation
  * Wiping practice

 * '''Vent Preparation '''
  * Clean clean-tools again
  * Cut some viton tips for spare earthquake stop screws
  * Alignment
   * Align the aux beam as a reference
   * All HV in vacuum off (Input/Output PZT)
   * Update snap shots: sus, strain gauges, IOO, OMC....etc (OMC has no strain gauges)
   * Recenter: IPANG/POS, oplevs with the mirrors fully aligned
  * Environment
   * Test drive crane drives
   * Keep eyes on particle counter: abort over 10,000
   * Look that we have good RGA scan

   * Chemicals: small bottles (like 250ml) / 3 bottles each (no matter how the size is), '''Acetone''' Spectral Grade, dehydrated (if possible), '''Isopropyl alcohol''' Spectral Grade, dehydrated (if possible)
   * glass sylinges with metal needles, 50ul, at least three sets
   * mirror wiping paper, usual lens paper from Kodak or whatever
   * tools (well cleaned)
   * clamps to mark the position of ITMX: 3pcs
   * halogen light or whatever: light during the work

 * '''Friday, 4 Dec: '''
  * Practice cutting viton, so we can get the correct sizes if we need to replace stops. (Jenne)
  * Recenter all of our pointing PDs (oplevs and IP_POS, IP_ANG). (DONE 10pm Friday)
  * Update snapshots of all MEDM screens that have alignment information. (DONE 10pm Friday)
  * Move extraneous equipment around chamber doors: Make sure we have clear access (esp. seismometers need moving) (DONE 5pm Friday)

 * '''Monday: '''
  * Before venting, check that all the recentering done on Friday is still good. If not, redo.
  * Vent
  * During vent, practice drag wiping a spare random optic (maybe a 2" CVI optic?)
  * Open ETMX
  * Take photos of ETMX before touching
  * Close up ETMX with light doors for the night

 * '''Tuesday: '''

 * '''Wednesday: '''

 * '''Thursday: '''

 * '''Friday: '''

Cleaning of the suspended test mass (Dec 2009)

Motivation

The round trip loss in the 40m cavity is estimated to be around 160ppm. We are going to confirm wether this comes from the hydrocarbon contamination and wiping of the mirror by acetone and isopropy may result in improvement of the optical loss, or not.

In addition we cna evaluate the use of those solvents. If we observe the degradation of the loss or the finesse, we will forbid them.

Measurements before the cleaning

- Visibility measurement

Most recent arm visibility measurement has been done on Oct 07, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2070 corresponding elog entry]

Measured arm reflectivity R_cav:
X arm: 0.875 +/- 0.005
Y arm: 0.869 +/- 0.006

- Cavity pole measurement

Most recent arm visibility measurement has been done on Nov 10, 2009. [http://nodus.ligo.caltech.edu:8080/40m/2226 corresponding elog entry]

Measured arm cavity pole frequency f_pole [Hz]:
X arm: 1720 +/- 70
Y arm: 1650 +/- 70

- Estimated finesse

Measurements after the cleaning

- Visibility measurement

- Cavity pole measurement

- Estimated finesse


Overview of the plan

  • We plan for the vent from 7th Dec to 11th Dec in 2009.

  • Preparation

    • Wiping Preparation

    • Vent Preparation

  • Monday:

    • Prevent check 8:00~
    • Vent from 9:30~
    • Stop venting ~14:00
    • Wipe ETMX 14:00~
      • Open ETMX 14:00~15:00
      • Mirror wiping 15:00~16:00
      • Check alignment / Close up 16:00~17:00
  • Tuesday:

    • (ETMX wipe)
    • ETMY wipe
    • ITMY wipe
  • ~ Wednessday:

    • ITMX position (pushing screws)
    • ITMX BB leveling
    • measure the distance of the breadboards
    • check of the optics in the chambers
  • Thursday:

    • Evacuation
  • Friday:

Detailed plan

  • ~Friday, 4 Dec:

    • Wiping preparation
  • Wiping Preparation

    • Wiping preparation
    • Wiping practice
  • Vent Preparation

    • Clean clean-tools again
    • Cut some viton tips for spare earthquake stop screws
    • Alignment
      • Align the aux beam as a reference
      • All HV in vacuum off (Input/Output PZT)
      • Update snap shots: sus, strain gauges, IOO, OMC....etc (OMC has no strain gauges)
      • Recenter: IPANG/POS, oplevs with the mirrors fully aligned
    • Environment
      • Test drive crane drives
      • Keep eyes on particle counter: abort over 10,000
      • Look that we have good RGA scan
      • Chemicals: small bottles (like 250ml) / 3 bottles each (no matter how the size is), Acetone Spectral Grade, dehydrated (if possible), Isopropyl alcohol Spectral Grade, dehydrated (if possible)

      • glass sylinges with metal needles, 50ul, at least three sets
      • mirror wiping paper, usual lens paper from Kodak or whatever
      • tools (well cleaned)
      • clamps to mark the position of ITMX: 3pcs
      • halogen light or whatever: light during the work
  • Friday, 4 Dec:

    • Practice cutting viton, so we can get the correct sizes if we need to replace stops. (Jenne)
    • Recenter all of our pointing PDs (oplevs and IP_POS, IP_ANG). (DONE 10pm Friday)
    • Update snapshots of all MEDM screens that have alignment information. (DONE 10pm Friday)
    • Move extraneous equipment around chamber doors: Make sure we have clear access (esp. seismometers need moving) (DONE 5pm Friday)
  • Monday:

    • Before venting, check that all the recentering done on Friday is still good. If not, redo.
    • Vent
    • During vent, practice drag wiping a spare random optic (maybe a 2" CVI optic?)
    • Open ETMX
    • Take photos of ETMX before touching
    • Close up ETMX with light doors for the night
  • Tuesday:

  • Wednesday:

  • Thursday:

  • Friday: