Differences between revisions 2 and 18 (spanning 16 versions)
Revision 2 as of 2011-06-06 20:52:28
Size: 468
Editor: KiwamuIzumi
Comment:
Revision 18 as of 2011-06-06 21:35:53
Size: 1818
Editor: KiwamuIzumi
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
= Interferometer Characterization =
== Goals and Motivations ==
= Interferometer Characterization at the 40m prototype =
== Goals ==
 . ''''' To help the DRMI commissioning that will be performed at LLO.'''''
== Motivations ==
 . In the aLIGO schedule ''''' a DRMI test will start on May 2011 at LLO. ''''' Prior to the DRMI test we, the 40m lab, should help their commissioning to make the things smooth and hence allow to finish the commissioning in shorter time. Moreover any commissioning tests that will be performed at LLO should be well predicted and tested at the 40m so that the people at the site can easily pass through all the commissioning tests and possibly can spend time for a real trouble shooting (commissioning) to fix unexpected issues.
 . So for this purpose some recipes must be prepared by the 40m lab. Each recipe includes descriptions about how to make a commissioning test, how to estimate important parameters and the results at the 40m. Additionally some useful scripts must be developed at the 40m.
Line 4: Line 8:
[[BR]]
Line 11: Line 14:
= Characterization Plan at the 40m =
== Schnupp asymmetry ==
= DRMI Characterization Plan at the 40m =
== Schnupp asymmetry measurement ==
=== Requirement ===
Line 17: Line 21:
== Cavity length == == Cavity length measurements==
=== Requirements ===
Line 22: Line 27:
== Recycling gains == == Recycling gain measurements ==
Line 27: Line 32:
== Sensing matrix ==
== Reflectivity check ==
Line 32: Line 38:
== Actuator responses ==
== Sensing matrix check ==
Line 36: Line 43:

== Calibration of Actuator responses ==
=== How to ===
=== Results ===
[[BR]]

== f2a filter adjustment ==
=== Requirement ===
=== How to ===
=== Results ===

[[BR]]
== IFO modeling ==
=== How to ===
=== Results ===

[[BR]]
== Estimation of Suspensions' Position ==
=== Requirements ===
=== How to ===
=== Results ===

[[BR]]
== Locking procedure ==
=== How to ===

Interferometer Characterization at the 40m prototype

Goals

  • To help the DRMI commissioning that will be performed at LLO.

Motivations

  • In the aLIGO schedule a DRMI test will start on May 2011 at LLO. Prior to the DRMI test we, the 40m lab, should help their commissioning to make the things smooth and hence allow to finish the commissioning in shorter time. Moreover any commissioning tests that will be performed at LLO should be well predicted and tested at the 40m so that the people at the site can easily pass through all the commissioning tests and possibly can spend time for a real trouble shooting (commissioning) to fix unexpected issues.

  • So for this purpose some recipes must be prepared by the 40m lab. Each recipe includes descriptions about how to make a commissioning test, how to estimate important parameters and the results at the 40m. Additionally some useful scripts must be developed at the 40m.

BR BR


BR

DRMI Characterization Plan at the 40m

Schnupp asymmetry measurement

Requirement

How to

Results

BR

== Cavity length measurements==

Requirements

How to

Results

BR

Recycling gain measurements

How to

Results

BR

Reflectivity check

How to

Results

BR

Sensing matrix check

How to

Results

BR

Calibration of Actuator responses

How to

Results

BR

f2a filter adjustment

Requirement

How to

Results

BR

IFO modeling

How to

Results

BR

Estimation of Suspensions' Position

Requirements

How to

Results

BR

Locking procedure

How to

Interferometer_Characterization (last edited 2012-03-11 03:31:49 by KiwamuizumiATligoDOTorg)