Line 1: Line 1:
= Green Laser Injection for Arm Pre-Lock = <<Anchor(TOP)>>
Line 3: Line 3:
We plan to install green lasers, which are phase locked to the PSL laser, at each end station to pre-lock the arm cavities before the lock acquisition.    . attachment:god_of_green.png




= Overview =

 The diagrams below show a conceptual design

   <<ImageLink(green_vertex_preliminary_design.png,Upgrade 09/GreenLock/Preliminary design for the vertex,height=200)>>
   <<ImageLink(green_ETM_preliminary_design.png,Upgrade 09/GreenLock/Preliminary design for the end,height=200)>>

= plans =

|| || ''' action item list ''' || [:Upgrade 09/GreenLock/action_item_list] ||
||<|15> ''' monthly plan ''' ||'''October 2010''' || [:Upgrade 09/GreenLock/October_2010] ||
||'''November 2010''' || [:Upgrade 09/GreenLock/November_2010] ||
||'''December 2010''' || [:Upgrade 09/GreenLock/December_2010] ||

[[BR]]

= developer's page =

||''' Optical Layout '''|| ([attachment:green_optics.png Table]/ In-vac) ||
|| ''' end table ''' || [[Upgrade 09/GreenLock/end table|ETM / end table]] ||
|| ''' end table ''' || <<ImageLink(endtable.jpg,Upgrade 09/GreenLock/end_table)>> ||
|| ''' wedge effect ''' || [[Upgrade 09/Optical Layout#wedge|ITM wedge effect]] ||
|| ''' in-vac ''' || [[Upgrade 09/Optical Layout|Periscopes for beam steering from PR3/SR3 transmissions to the PSL viewport]] ||
|| ''' Mode matching ''' || ([attachment:modematch_END.png mode matching at end table]) ||
|| ''' Electronics ''' || [:Upgrade 09/GreenLock/Electronics] ||
|| ''' sensing and control ''' || [[Upgrade 09/GreenLock/Control Information|jump to Control Information]] ||
|| ''' manual for the doubling oven ''' || [attachment:manual_oven.pdf manual for the covesion oven] ||
|| ''' noise requirements ''' ||[:Upgrade 09/GreenLock/Noise Requirement] ||
|| ''' purchase list ''' || [[Upgrade 09/Purchase List/Green Locking|Purchase list]] ||
  


= links =
|| ''' aLIGO ALS wiki ''' || http://ilog.ligo-wa.caltech.edu:7285/advligo/Arm_Length_Stabilisation ||
|| ''' Description of the optical / servo configuration ''' || [https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=6888 LIGO DCC] ||
|| ''' Servo modeling (!SimLink) ''' || [https://nodus.ligo.caltech.edu:30889/svn/trunk/docs/upgrade08/Green_Locking/Servo_modeling/ 40mSVN] ||

  • attachment:god_of_green.png

Overview

  • The diagrams below show a conceptual design
    • green_vertex_preliminary_design.png green_ETM_preliminary_design.png

plans

action item list

[:Upgrade 09/GreenLock/action_item_list]

monthly plan

October 2010

[:Upgrade 09/GreenLock/October_2010]

November 2010

[:Upgrade 09/GreenLock/November_2010]

December 2010

[:Upgrade 09/GreenLock/December_2010]

BR

developer's page

Optical Layout

([attachment:green_optics.png Table]/ In-vac)

end table

ETM / end table

end table

endtable.jpg

wedge effect

ITM wedge effect

in-vac

Periscopes for beam steering from PR3/SR3 transmissions to the PSL viewport

Mode matching

([attachment:modematch_END.png mode matching at end table])

Electronics

[:Upgrade 09/GreenLock/Electronics]

sensing and control

jump to Control Information

manual for the doubling oven

[attachment:manual_oven.pdf manual for the covesion oven]

noise requirements

[:Upgrade 09/GreenLock/Noise Requirement]

purchase list

Purchase list

links

aLIGO ALS wiki

http://ilog.ligo-wa.caltech.edu:7285/advligo/Arm_Length_Stabilisation

Description of the optical / servo configuration

[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=6888 LIGO DCC]

Servo modeling (SimLink)

[https://nodus.ligo.caltech.edu:30889/svn/trunk/docs/upgrade08/Green_Locking/Servo_modeling/ 40mSVN]

Advanced_Techniques/Green_Locking (last edited 2015-06-23 03:44:00 by EricquinteroATligoDOTorg)